Australia’s M113 APC Family Upgrades
Related Stories: Australia & S. Pacific, BAE, Contracts - Awards, Contracts - Modifications, Electronics - General, Guns - under 20mm direct, Official Reports, Other Corporation, Partnerships & Consortia, Policy - Procurement, Support Functions - Other, Tanks & Mechanized, Testing & Evaluation
The M113A1 family of vehicles was introduced into service in Australia in the mid 1960s, and arrived in time to see service in Vietnam. Additional vehicle variants were added until 1979, and there are 766 M113A1 vehicles currently in the Australian Army fleet. By February 2005, however, only 520 remained in service.
A number of upgrades have been suggested for Australia’s APCs over the years, with a number of different reviews and upgrade proposals submitted. Many of Australia’s M113s remain in M113A1 configuration, with some having undergone repair and overhaul at 25,000 km. Bushmaster wheeled mine-resistant vehicles have replaced some M113s, but the M113’s lightweight, tracked, off-road mobility remains important to Australian mechanized formations, and to troops deployed in combat zones.
A plan approved in the late 1990s involved a “minimum upgrade” of 537 vehicles from 1996-1998, at a cost of about A$ 40 million in 1993 dollars, with a major upgrade to follow. That was derailed mid-stream by an unsolicited contractor proposal to combine the 2 phases. The end result was Australia’s LAND 106 project, which aimed to perform major upgrades to 350 M113 APCs. That program suffered from problems in its early stages, delaying any fielded modernization until 2007, but the program is said to be back on track now.
The new Labor government has just added emphasis to that assessment, by expanding the program as part of Australia’s push for a “Hardened and Networked Army.” But Australia’s National Audit Office sees both substantial progress, and serious problems, with the program.
- The New Vehicles
- The Program
- Contracts and Key Events [updated]
- Aditional Readings
The New Vehicles
There are 7 variants of the upgraded M113AS family being produced under LAND 106. Enhancements are being made to a variety of areas.
Protection: Add-on external armor kits to protect against weapons up to 14.5mm; internal spall liners; hull reinforcement to improve mine protection; fuel tanks moved from inside to outside. The change in configuration also allowed the introduction of stealth characteristics into the design by decreasing the overall turret profile, and reducing the vehicle’s radar cross-section and infra-red signature.
Firepower: A new Australian designed and built electrical turret, with improvements designed to lessen the battering its occupant takes. It will host a new .50 caliber weapon that sports a quick change barrel and day/night sights.
Mobility: Replacement of the engine, transmission, drive train and driver’s controls. To maximize the benefits of this new driveline, the suspension, track and road wheels are also being replaced.
Internal: Compartment improvements like heat mitigation measures and better stowage of equipment externally where it isn’t so much in the way. New electrical and fuel systems; a land navigation system that combines GPS and INS.
The exact designations refer to the upgraded vehicles’ general characteristics. M113-AS3 variants have 5 road wheel stations per side, and a Recommended Gross Vehicle Mass of 15,000 kg/ 33,069 pounds. AS4 variants are stretched by 666 mm/ 26.2”, with 6 road wheel stations per side, and an RGVM of 18,000 kg/ 39,683 pounds. Variants include:
- Armoured Personnel Carrier (M113-AS4 APC). Most common variant.
- Armoured Fitters (M113-AS4 AF). Includes a new Hiab crane with a significantly enhanced 2.4-tonne lift at 4 meters. 38 planned of 350.
- Armoured Recovery Vehicle Light (M806-AS4 ARVL). Includes a Sepson winch capable of a 13-tonne single line pull. 12 planned of 350.
- Armoured Ambulance (M113-AS4 AA)
- Armoured Command Vehicle (M113-AS4 ACV)
- Armoured Logistic Vehicle (M113-AS4 ALV)
- Armoured Mortar (M125-AS3 AM)
The Program
As noted above, the M113 upgrade program was initially envisaged as having a minimum upgrade stage and a follow-on upgrade phase. That was eventually collapsed in to one major LAND 106 upgrade of fewer machines, in an intended cost saving measure. The operational effect was to delay fleet upgrades by about a decade.
The LAND 106 M113 Upgrade was scheduled to be completed in 3 stages, and delivery of the first company group of upgraded M113s was scheduled for 2006.
Stage 1: Development and preliminary testing of 2 Demonstration vehicles. Completed in 2004.
Stage 2: Design, construction and testing of the first 14 of the Initial Production Vehicles (IPV). This stage encountered a number of technical difficulties, resulting in an extensive Test and Evaluation Phase. Delivery of the initial 16 Phase 1 & 2 vehicles (14 APCs, 1 AF and 1 ARVL) to the 1st Brigade in Darwin was completed in December 2007.
Design development of the remaining 4 vehicle variants will continue through to the end of 2009.
Stage 3: Design, construction and testing of the remaining IPVs, and the delivery of 336 production standard vehicles. Began with successful completion of the Production Readiness Review in November 2007.
Tenix chose Germany’s FFG as the major technology partner for the program. Other key subcontractors and suppliers include Thales Optronics, Moog GmbH, SKF Australia, Bisalloy and a number of Australian SMEs including Imag Australia Pty. Limited.
When Tenix’s land systems business was acquired by BAE Systems, it was easy for the vehicle’s original manufacturer (United Defense, now the largest part of BAE Land Systems) to assume leadership of the project via its new subsidiary.
Contracts and Key Events
March 27/09: The Australian National Audit Office (ANAO) issues “Management of the M113 Armoured Personnel Carrier Upgrade Project.” The 2009 ANAO report praises progress in a number of problem areas that were highlighted in the 2005 report. The 2007 renegotiation and restructuring has helped the program make significant progress in key areas, from management, to technical development. Having said that:
“The M113 Major Upgrade Project commenced in July 2002 and has suffered a series of delays. Army has so far received 42 of the 350 vehicles to be upgraded [which is behind schedule].... In July 2008, the Prime Contractor informed Defence that the existing production facilities at Bandiana, Victoria, were not adequate to the task and, at December 2008, there was a potential shortfall of around 100 upgraded vehicles by December 2010.
The backlog is caused chiefly by delays in extending the hulls. This is proving to be more complex than anticipated, and is taking longer than expected….. would not be able to deliver 350 upgraded vehicles by December 2010. Defence is currently negotiating arrangements with the Prime Contractor….”
Oct 28/08: Australia’s Labor Party government announces an A$ 220 million (currently about $143 million) addition to LAND 106. BAE will upgrade another 81 M113s to equip Darwin’s 5 RAR mechanized infantry and the recently established 7 RAR, raising the total to 431 vehicles.
BAE Systems’ production line at Bandiana in northern Victoria will now remain open until July 2011, and additional facilities will be opened in Williamstown, Victoria and Wingfield, South Australia to ensure that delivery commitments are met.
May 22/08: The LAND 106 project is reported to be back on track. Frontier India:
“The M113 project experienced some well-known technical problems in the development phase, and it was feared these problems would impact on the cost and schedule of the project,” the announcement said. The serious technical risks faced by the project have now been resolved, the schedule pressures have been reduced, and the project does not face cost pressures said the release.”
Nov 15/07: The first 4 M113AS4s built by Tenix Aerospace and Defence are accepted into service with the Australian Army’s 7th Battalion, The Royal Australian Regiment (Mechanised Infantry), during a ceremony in Darwin. Australian DoD | Space Daily.
June 11/06: Australia’s DMO contracts with Honeywell Germany to supply the new TALIN 500 Inertial Navigation Unit for the M113 vehicles at a cost of A$ 11 million.
Acquired under Project JP5408, the TALIN 500 is the central component of the new navigation system for the M113s, integrating a global positioning system (GPS) with the inertial navigation functions as a backup if GPS isn’t available. The new system will provide full navigation capability to both the commander and driver of the M113. DMO believes the system has export potential. DoD release | DMO On Target article.
July 28/05: The Australian National Audit Office (ANAO) report criticizes Australia’s management of its M113 upgrade program, beginning with the 3-year delay between project approval in June 1999 and the July 2002 contract and continuing to the present day. The report add that the November 2006 goal for introduction into service is unlikely to be achievable. ANAO report | Jane’s
July 15/02: Australia’s Liberal Party government announces an A$ 400 million (then about $223.5 million) contract with Tenix Defence Land Division to upgrade 350 M113 tracked armored fighting vehicles to M113-AS4 configuration. Imag Australia Ltd. Pty release.
June 2002: The M113 Major Upgrade Project is approved at a cost of A$ 552 million (ANAO figure).
Additional Readings and Sources
- Australian DMO – LAND 106 – M113 Upgrade Project
- ANAO (March 27/09) – Management of the M113 Armoured Personnel Carrier Upgrade Project
- ANAO (July 28/05) – Management of the M113 Armoured Personnel Carrier Upgrade Project
- Digger History – “The Tracks”: A Digger’s Best Heavy Metal. Includes history of the M113 in Australian service.
- Australian DoD, Team Australia – Mackay Defence Technologies: armoured vehicles – vibration and noise isolation (APC floor mats)
- Jane’s – BAE Systems Australia one-man turret for M113 APC upgrades (Australia), AFV turrets and cupola
- Army: The Soldiers Newspaper (#1169, June 28/07) – Now that’s better. Discusses firing trials of the new electric turret.
- Army: The Soldiers Newspaper (Ed. 1151, July 27/06) – A fitting display. Discusses the M113-AS4 FV and ARVL.
- Army: The Soldiers Newspaper (#1135) – New M113 on track







