KC-46A Pegasus Aerial Tanker Completes Firsts

KC-135 plane

KC-135: Old as the hills…
(click to view full)

DID’s FOCUS articles cover major weapons acquisition programs – and no program is more important to the USAF than its aerial tanker fleet renewal. In January 2007, the big question was whether there would be a competition for the USA’s KC-X proposal, covering 175 production aircraft and 4 test platforms. The total cost is now estimated at $52 billion, but America’s aerial tanker fleet demands new planes to replace its KC-135s, whose most recent new delivery was in 1965. Otherwise, unpredictable age or fatigue issues, like the ones that grounded its F-15A-D fighters in 2008, could ground its aerial tankers – and with them, a substantial slice of the USA’s total airpower.

KC-Y and KC-Z buys are supposed to follow in subsequent decades, in order to replace 530 (195 active; ANG 251; Reserve 84) active tankers, as well as the USAF’s 59 heavy KC-10 tankers that were delivered from 1979-1987. Then again, fiscal and demographic realities may mean that the 179 plane KC-X buy is “it” for the USAF. Either way, the KC-X stakes were huge for all concerned.

In the end, it was Team Boeing’s KC-767 NexGen/ KC-46A (767 derivative) vs. EADS North America’s KC-45A (Airbus KC-30/A330-200 derivative), both within the Pentagon and in the halls of Congress. The financial and employment stakes guaranteed a huge political fight no matter which side won. After Airbus won in 2008, that fight ended up sinking and restarting the entire program. Three years later, Boeing won the recompete. Now, they have to deliver their KC-46A.

Boeing’s KC-46A, and Its Team

Concept: KC-46A refuels Super Hornets

KC-46A concept
(click to view full)

KC-46A Pegasus production takes place in 2 phases: the 767-2C, and then the militarized KC-46A modifications.

There are still a number of things we don’t know, though more details have emerged since Boeing won the competition. The first step is to build a 767 on the commercial production line with a cargo door and freighter floor, an advanced flight deck display borrowed from its new 787, body tanks, and provisions for aerial tanker systems. Initial Boeing graphics featuring upturned winglets on the wingtips are no longer part of the design, but Pratt & Whitney’s 62,000 pound thrust PW4062s remain their engine choice. This is the 767-2C, and it receives an FAA 767 amended Type Certificate.

The 767-2C is militarized in a separate finishing center by adding aerial refueling equipment, an air refueling operator’s station that includes panoramic 3-dimensional displays, and threat detection/ countermeasures systems. The resulting KC-46A receives an FAA 767 Supplemental Type Certificate given to substantially different variants, and must also receive USAF certification that clears the way for full acceptance.

Boeing’s refueling boom is derived from the KC-10’s AARB, but adds 3-D viewing and a slightly higher fuel offload rate of 1,200 gallons/min. The centerline and wing-mounted refueling pods will now come from Cobham plc’s Sargent Fletcher, who was also partnered with Airbus for this feature. Unlike the A330 MRTT’s systems, however, the KC-46A’s wing refueling pods still need to finish testing on the 776-2C. The USAF will buy 46 wing sets for its fleet, which will allow multi-aircraft (multipoint) aerial refueling when installed.

KC-46A cargo capacity lists as 65,000 pounds, in a mix of up to 18 cargo pallets, 114 passengers, and/or 58 medical stretcher slots.

KC-X comparison: KC-135, KC-10, KC-46A 767, KC-45A A330

Fielding a tanker built after the 1960s allows the USAF to include a number of new systems, which would be too costly to retrofit into the existing KC-135 fleet. The net effect is to make its KC-46As front-line refuelers. The cockpit and exterior lighting are night-vision compatible for covert rendezvous. Advanced communications and secure datalinks are big steps forward for the fleet, and their classified feeds will be used by specialized ESTAR and TCS systems designed to route the tanker away from threats. NBC (nuclear, biological, chemical) protection will allow the planes to operate in contaminated environments, while EMP hardening reduces the effects of high-frequency radiation bursts on all those new solid-state electronics. On a more prosaic level, radar warning systems, infrared defensive systems, cockpit armor, and fuel tank ballistic protection will all be welcome.

KC-46A Industrial Team

KC-X Round 1 team

Boeing’s KC-X 1.0 Team

Boeing’s industrial team has slowly announced itself over many months since the award. American KC-46A content has been touted as high as 85%, with British firms picking up much of the balance. Boeing reportedly looked hard for supply chain savings in Round 2, though, in order to lose less money with its under-cost bidding strategy.

That KC-46A design is a big change from KC-X round 1, whose KC-767 Advanced used a 767-200ER fuselage; a 767-300F freighter wing, landing gear, cargo door and floor; and a 767-400ER’s flaps and flight deck (derived in turn from the 777). A new design fly-by-wire boom with remote viewing would expand the tanker’s effective refueling airspace, and offload more fuel. Engines would be 2 Pratt & Whitney PW4062s, with 62,000 pounds of thrust each, instead of the KC-767A/J’s 60,200 pound CF6-80C2s.

Boeing's KC-46A Industrial Team

Some of the suppliers also changed, as Boeing progressed from the canceled KC-767 lease deal, to KC-X, to its final design in Round 2:

KC-767 to KC-46A: M.I.A.

Boeing’s production line had also progressed. Near the end of the KC-X bidding, Boeing added civilian 767 orders to keep its production line going. That was enough to create a cushion if KC-X faced further challenges and issues, but the reality is that civilian 767 production looks set to end soon. The US military will soon become the 767 production line’s sole support.

KC-X: The Program

A March 2012 GAO report summed up the risk driving the KC-46A program, and the current state of the USAF’s tanker fleets:

“According to the Air Force, the national security strategy cannot be executed without aerial refueling… the KC-135 Stratotanker, is over 50 years old on average and costing increasingly more to maintain and support. With… more than 16,000 flight hours on each aircraft, the KC-135s will approach over 80 years of age when the fleet is retired as projected in the 2040 time frame. In 1981, the Air Force began supplementing its fleet of KC-135s with [59] KC-10s… that transport air cargo and provide refueling. Much larger than the KC-135, the KC-10 provides both boom and hose and drogue refueling capabilities[Footnote 4] on the same flight and can conduct transoceanic missions. The KC-10s now average about 27 years of age with more than 26,000 flight hours on each, and their service life is expected to end around 2045.”

KC-46A Program Overview Figures

The $7.2 billion October 2012 development cost estimate includes $4.9 billion for the aircraft development contract and 4 test aircraft, $0.3 billion for the aircrew and maintenance training systems, and $2 billion for other government costs and some risk funds. The total procurement cost estimate of $40.46 billion in base-year dollars buys 175 production aircraft, initial spares, and other support items as priced in contract options.

Cost estimates as of April 2014 are stable, with an estimated $1.6 billion to cover other government costs like program office support, test and evaluation support, contract performance risk, and other development risks. That includes the cost of test flights, which will sometimes feature operational military aircraft of various kinds to act as receivers.

An accompanying military construction estimate of $4.2 billion includes the projected costs to build aircraft hangars, maintenance and supply shops, and other facilities to house and support the full 175-plane KC-46 fleet at up to 10 main operating bases (McConnell AFB, KS is MOB1), 1 training base at Altus AFB, OK; and the Oklahoma City Air Logistics Complex depot.

The KC-46A Development Phase: Budgets, Splits, & Dates

KC-X/ KC-46A Budgets: 2011-2018

[youtube:v=gNC0cQJicYg]

KC-46 development

The Pentagon’s latest Selected Acquisition Report estimates a total KC-46A development cost of $5.615 billion, which would actually be $1.221 billion over the KC-X EMD phase’s original Target Cost of $4.394 billion. Fortunately for the USAF, they structured the contract so they can’t pay more than $4.7 billion, and the overall bid cost to the US government for development plus production remains below Airbus’ bid.

Here’s how it works:

* Up to the $4.898 billion ceiling, the contract split for amounts over the $4.394 billion base price is 60/40. The difference is $504 million, so the government would pay $302.4 million ($4.696 billion total), and Boeing would pay about $201.6 million.

* Costs above the $4.898 billion ceiling are all Boeing’s responsibility.

Current estimates show that there’s almost no chance of coming in under the ceiling. Boeing’s current cost estimate is $5.164 billion, which would raise its private liability for the cost increases to $467.5 million (201.6 + all 265.9 over the ceiling). If the government program manager is right, Boeing’s liability rises to $918.6 million (201.6 + all 717.0 over). The difference matters to Boeing, but the Pentagon doesn’t have to care which EMD Phase figure is correct, or how much higher EMD costs go. Their costs are set, at $4.7 billion, though actual dollars will be a bit higher due to inflation etc.

That’s if, and only if, the USAF doesn’t start asking for design changes. If they do, that would trigger a cycle of charges over and above the agreed contract.

As of December 2012, schedule planning looked like this:

USAF KC-46A schedule as of December 2012

Concurrence concerns

The USAF has maintained its Q4 FY 2015 (summer 2015) goal for a successful Operational Assessment and Milestone C decision, and this remains the official target. Success which would clear the way for 2 firm-fixed-price Low-Rate Initial Production (LRIP) lots to deliver the initial 19 aircraft. Full-Rate Production options would follow beginning in FY 2017 as a firm-fixed-price contract with some adjustments for outside circumstances, and a not-to-exceed cap. The USAF will be assessing the possibility of breaking out the engines as a separate government procurement in FRP, instead of having Boeing provide them.

As Airbus predicted when the contract was awarded, however, Boeing has admitted to trouble meeting these development milestones. The schedule will need to be changed, but there’s no official replacement schedule yet.

The schedule may need to incorporate other changes as well. The Pentagon’s own DOT&E testers have doubted proclaimed Initial Operational Test and Evaluation (IOT&E) dates (Q3 FY 2016 – Q1 2017) for some time. Beyond technical issues that have slowed the new design, testing must avoid revealing significant problems.
Initial Operational Capability (IOC) was pegged for August 2017, with Full Operational Capability (FOC) expected by August 2019, but USAF Air Mobility Command is no longer giving official target dates.

The program as a whole is expected to end by 2028.

The KC-46A Production Phase: Risks & Numbers

KC-10 & F/A-18C over Afghanistan

KC-10 & F/A-18C

The current program calls for Boeing to begin delivering KC-46As to the USAF by 2015. Unfortunately, the KC-46A is too different from previous KC-767A models sold to Japan and Italy, so it will need its own development, testing, and certification time. That’s why Airbus and program skeptics have always doubted that Boeing could deliver 18 certified, fully developed and tested planes by 2017. Boeing disputes this, but the Pentagon’s own DOT&E office added weight to those concerns in its 2011 reports, which declared the KC-46A’s test program “not executable.” That continues to be a concern.

Beyond basic integration and certification considerations, a March 2012 GAO report cites 6 key technical risks to the program:

1. Weight limits. The KC-46A is close to its limit, and any more growth will start to take away fuel capacity, while increasing fuel burn rate. As of December 2013, Boeing remains confident that they will remain under the maximum take-off weight of 204,000 pounds.

2. New wing refueling pods. The KC-46’s pods will be redesigned to reduce buffeting of the aircraft’s wing, and change the way the refueling hose exits the pod. Still a technical risk as of December 2013.

3. 3-D display for the boom operator.

4. Threat Correlation Software. Used to help plot safe routes, along with the…

5. ESTAR software.

6. ALR-69 Radar Warning Receiver integration. Issues like figuring out precise placement, and antenna design, make fitting a large aircraft more challenging than many people expect.

Problems with these or other systems could delay the program further, and some of these issues could also make certification harder or longer. Even so, the actual risk that set the development program back wasn’t any of these. It was the need to redesign certain wiring sections for military-grade shielding requirements and mandatory separation distances.

Meanwhile, the USAF plans to respond to continued budget cuts by removing their existing KC-10 heavy refuelers entirely, adding tremendous risk by removing their inherent boom/hose versatility, and leaving no tanker alternative if the KC-135s develop a serious problem.

Fleet Risks

USAF KC-46A/ KC-135 Force Structure: 2011 plans + Actual

Over the longer term, plotting even a 3-year production delay against planned deliveries and KC-135 retirements never drops the medium tanker fleet much below present levels. The initial drop is slight, and the same final figure is reached in 2030 instead of 2027. On the other hand, RAND’s 2006 Analysis of Alternatives for KC-X highlighted a very different risk, which needs to be understood:

“The current (December 2005) assessment of the flight-hour life of the KC-135 fleet and the expected future flying-hour programs together imply that these aircraft can operate into the 2040s. It cannot be said with high confidence that this is not the case, although there are risks associated with a fleet whose age is in the 80- to 90-year range. It can also not be said with high confidence that the current fleet can indeed operate into the 2040s without major cost increases or operational shortfalls, up to and including grounding of large parts of the fleet for substantial lengths of time, due to currently unknown technical problems that may arise. The nation does not currently have sufficient knowledge about the state of the KC-135 fleet to project its technical condition over the next several decades with high confidence.”

In English, nobody knows if an airplane fleet that’s already 50 years old will remain safe, or avoid unforeseen mechanical or structural problems, because there’s no previous example of what they’re trying to do. Those kinds of sudden “age-out” problems recently grounded the USAF’s F-15A-D fleet for several months, and led to the unexpected retirement of almost 1/4 of the fleet. If anything similar happens to the KC-135, the USAF’s planned number of aerial tankers may not resemble its actual future fleet.

This risk, and the potential absence of the KC-10, is exactly why the KC-X program has been the USAF’s #1 priority. On the other hand, it’s an equally good reason not to trust the USAF’s own rosy projections for its future fleet size. The graph below shows how this kind of scenario could play out. In DID’s hypothetical example, we used actual data to the present day, plus all planned reductions in the USAF’s 2011 plan. Fleet problems lead to the forced retirement of 1/3 of the remaining fleet in 2021 over safety and cost-to-fix issues, followed by a second mechanical issue or budget crisis that grounds another 55 planes in 2029. The KC-10 fleet is not part of this calculus at all.

The USA’s looming fiscal entitlements crisis will begin to bite in earnest post-2020, and the pattern of cuts in the USA and in other countries shows a marked tendency to simply retire platforms with significant maintenance costs. KC-135 per-hour flight costs are already increasing, and a fleet that also needed expensive refits or fixes would be a prime target for future cuts. Here’s what this scenario looks like:

USAF Tanker Force Structure: Age-Out & Cuts Scenario

Finally, DID believes that there will be no KC-Y or KC-Z, so the timing of KC-135 problems and retirements isn’t critical. Any serious problems in the KC-135 fleet could create a similar end-point, even if the drops happened after 2030.

KC-46A Export Prospects

[youtube:v=LnlonUtv3cM]

IAI’s KC-767 MMTT

Once the KC-46As do enter service, they will join Italy’s KC-767A (4) and Japan’s KC-767J (4) small KC-767 fleets. Both customers have experienced long delivery delays while Boeing has worked to iron out technical problems, and their KC-767s will have a number of key differences from the KC-46A. Japan’s boom-equipped KC-767s were delivered form 2008-2010, but Italy’s aircraft with hose-and-drogue systems were only accepted in February 2011.

That’s one option, if Boeing will produce the planes.

The KC-46A’s schedule and dwindling civil 767 production are problematic for export orders, because the USAF will be Boeing’s sole focus until the EMD Phase is done in 2017 – or later. Countries that need aerial tankers before 2019-2020 will need to look elsewhere. Boeing declined to bid on India’s aerial tanker RFP, for instance. There’s also a customer commitment issue. Should customers accept the KC-767A, which is certified and in service, or wait for the KC-46A, and hope it’s on time?

Airbus sees this lock-up as an opportunity to add to its A330 MRTT customer list, of course, signing customers like India, Qatar, and Singapore. Ironically, the other big beneficiary may by Israel’s IAI Bedek, whose inexpensive KC-767 MMTT conversion of used Boeing freighters already has customers in Colombia and Brazil.

As of June 2013, Boeing was reportedly pursuing prospects for up to 20 aerial tanker exports. If so, they have been quiet pursuits. The next big opportunity will be in South Korea.

KC-X: Contracts & Key Developments

FY 2016 – 2025

 

KC-46A boom assembly

Boom assembly
August 27/25: Israel plans to acquire two Boeing KC-46 aerial refueling tankers in a deal worth about $500 million. The purchase will be financed through US military aid, pending approval from an Israeli ministerial committee for defense procurement. Israel already operates four KC-46s, delivered under earlier contracts. Defense Ministry Director General Amir Baram said the tankers will bolster the Israeli Air Force’s ability to conduct long-range operations. The ministry noted that the new aircraft will be integrated with Israeli systems, though it did not specify which.
June 4/25: Turkeyis deciding between Boeing’s KC-46A Pegasus and the Airbus A330 MRTT (Multi Role Tanker Transport) to replace its retiring KC-135 tanker aircraft, a Turkish official with knowledge of the matter told Breaking Defense. The choice “to buy the new tanker [is between] MRTT and KC-46,” the official said, adding the negotiations are ongoing with both sides. However, the official didn’t specify the number of tankers in demand or the timeline of any prospective deal.
November 18/24: The 56th Air Refueling Squadron has unveiled the world’s first KC-46 Pegasus demonstration team at the Wings and Warriors Fly-In in San Marcos, Texas, on November 9. This debut performance marked a major milestone for the KC-46, highlighting its advanced capabilities and the crucial role it plays in modern air operations. The demonstration team, composed of pilots, boom operators, and maintenance personnel, showcased the KC-46’s impressive performance and versatility. Spectators were treated to a thrilling display as the aircraft executed a high-speed pass with its refuelling boom extended at 500 feet, followed by a low-speed pass with its landing gear and flaps deployed. These manoeuvres effectively illustrated the aircraft’s agility and precision, crucial attributes for a tanker operating in challenging environments.

October 8/24: The US Air Force has selected seven bases as candidate locations for the KC-46A Pegasus aircraft, with the final decision set for 2027. The main operational site will be chosen from Bangor Air National Guard Base in Maine, Forbes Field Air National Guard Base (Topeka) in Kansas, Key Field Air National Guard Base (Meridian) in Missouri, and McGhee Tyson Air National Guard Base (Knoxville) in Tennessee.

April 11/24: FlightSafety International Defense Corp. won a $7.9 million modification for the exercise of the KC-46 Aircrew Training System. The contract modification will provide an additional weapon system trainer, additional learning management workstations, systems engineering and program management, as well as new refresher training scenarios. Work will be performed at Broken Arrow, Oklahoma, and is expected to be completed by July 2026.

November 30/23: USAF Boeing has received a $2.3-billion deal to build 15 more KC-46A Pegasus tanker aircraft for the US Air Force. Announced Tuesday, the agreement would allow the service to bolster its aerial refueling and cargo transport capacities. According to company vice president Lynn Fox, the new order reflects the air force’s trust in the capability of the tanker aircraft.

September 2/22: Lot 8 Boeing won a $2 billion contract modification for KC-46A Air Force Production Lot 8 aircraft, subscriptions and licenses. The contract modification provides for the exercise of an option for an additional quantity of 15 KC-46A aircraft, data, subscriptions and licenses being produced under the basic contract. Work will take place in Washington. Expected completion date is November 30, 2025.

June 17/22: Wireless The Defense Advanced Research Projects Agency (DARPA) published a request for information on June 14 seeking industry feedback on a concept to wirelessly recharge unmanned air vehicles using a high-powered laser mounted on an external pod. Agency officials want industry feedback on the possibility of retrofitting aerial refueling aircraft like the Air Force’s KC-46 and KC-135 with “an underwing power beaming pod” to wirelessly recharge a fleet of unmanned aerial systems. The benefits of having drones recharge their batteries in mid-air include extended range and having small energy storage capacities.

May 11/22: 24.2 Hour Long Flight A US Air Force KC-46A crew has flown the aerial refueling aircraft for 24.2 hours in a mission to gather human factors data on long-duration flights. The aircraft was flown by four pilots working on four-hour shifts with another two pilots acting as backup. They were joined by three boom operators, a photojournalist, and a physician assistant. Taking off from McConnell Air Force Base on May 5, the jet landed back at McConnell Air Force Base the next day with just one refueling from a KC-46A.

April 29/22: Foreign Refueling During an Employment Concept Exercise in Spain, the US Air Force’s KC-46A carried out the first operational refueling of a foreign aircraft on April 18. The aerial refueling tanker passed fuel to Spanish Hornets during the flight. Four KC-46A tankers are deployed to Moron Air Base for this Employment Concept Exercise.

April 11/22: Support Boeing won a $55.5 million deal in support of the KC-46 program. This was a sole-source acquisition using justification 10 US Code 2304 (c)(1), as stated in Federal Acquisition Regulation 6.302-1. Boeing will deliver the entire KC-46 tanker fleet by 2027. The programme is expected to generate more than 50,000 jobs and will involve about 800 suppliers. Work under the current deal will be performed in. Missouri. Estimated completion date is April 6, 2025.

January 25/22: ATS FlightSafety International won a $32 million contract for the exercise of the KC-46 Aircrew Training System (ATS) Production Year 7 options. The contract modification is for the exercise of option contract line item numbers for additional weapon system trainers, boom operator trainers, fuselage trainer, pilot part task trainers, support equipment, McChord site activations, systems engineering and program management, summative evaluation and new refresher training scenarios. Work will take place in Oklahoma. Estimated completion date is January 7, 2024.

January 4/22: Israel The Israel Ministry of Defense inked an agreement estimated to be worth $3 billion with the United States for CH-53K helicopters and KC-46 refueling aircraft. On Friday, the ministry said in a statement that it is ordering 12 helicopters built by Sikorsky, a subsidiary of Lockheed Martin, as well as two tanker aircraft. It is part of an upgrade of Israel’s air force capabilities and includes an option to buy six additional helicopters.

December 15/21: Israel Israeli media says Tel Aviv asked Washington for the immediate delivery of two KC-46A aerial refueling tankers. The original schedule is for Israel to receive the first two tankers in 2023. However, the United States reportedly denied the request. Back in July 2020, it was reported that Israel had also asked for the delivery of the planes to take place this year.

December 9/21: Five More To Refuel The US Air Force Air Mobility Command approved the operation of KC-46A Pegasus to refuel five more aircraft: AC-130J Ghostrider, HC-130J Combat King II, MC-130J Commando II, C-5M Super Galaxy and E-3G Sentry. On December 6, Gen. Mike Minihan, commander of Air Mobility Command, approved a fourth Interim Capability Release (ICR) mission set for the KC-46A allowing it to refuel five types of aircraft.

November 2/21: Japan Boeing said it delivered the first KC-46A tanker to the Japan Air Self-Defense Force (JASDF) marking the program’s first delivery to a customer outside the United States. The KC-46A has already completed more than 5,000 sorties and transferred more than 50 million pounds of fuel to other aircraft through its boom and drogue systems.

October 21/21: F15 and F-16 The Boeing-made KC-46A Pegasus multirole tanker has been given the green light to refuel all versions of F-15 and F-16 fighter jets. Gen. Mike Minihan, commander of Air Mobility Command, approved a third Interim Capability Release (ICR) mission set for the KC-46A Pegasus, on October 13. This ICR decision allows the KC-46 to refuel all variants of the F-15 Eagle and F-16 Fighting Falcon during US Transportation Command tasked missions.

September 20/21: Mission Planning Center J.I. Gascia Construction won a $7.6 million task order under a multiple award construction contract for a design-build KC-46A mission planning center at Travis Air Force Base, California. The work to be performed will provide a facility to support KC-46A mission planning. The contract contains four options, which requires the contractor to repair sewer line, construct the window infill, perform hazardous material remediation, and construct physical security upgrades at the mechanical yard. The KC-46A is a wide-body, multi-mission aircraft capable of transporting fuel, cargo, passengers, and patients. Work will take place in California. Expected completion will be by December 2022.

 

September 10/21: Fuel Hydrants The Ross Group won a $10.6 million deal, which provides services for the phased demolition and construction of selected Ramp 200 and 300 fuel hydrants for KC-46A aircraft. The new work includes, but is not limited to, modify the current aircraft parking layout, demolish four existing aircraft direct fueling stations, demolish and replace six aircraft direct fueling stations suitable for KC-46A aircraft refueling operations, modify the existing fuel piping laterals, demolish and replace aircraft rated pavement on Ramps 200 and 300, as required, to demolish and install new hydrant pits and fuel piping, provide mooring points at all KC-46A parking spaces, and re-stripe aircraft parking positions and movement lanes on the 200 and 300 ramps. The KC-46A is a wide-body, multi-mission aircraft capable of transporting fuel, cargo, passengers, and patients. Work will take place in California and is expected to be finished by September 2022.

 

August 18/21: Tanker To Tanker Japan’s first KC-46A recently refueled another KC-46A over the state of Washington. “Refueling with the first Japan KC-46A is an important milestone for the Japan Air Self-Defense Force,” Jamie Burgess, KC-46 program manager, said in a statement from Boeing. Japan is the first non-US KC-46A customer, and is scheduled to receive its first tanker later this year.

 

August 9/21: 2nd ICR On August 5, US Air Mobility Command commander Gen. Jacqueline Van Ovost approved a second Interim Capability Release (ICR) mission for the KC-46A Pegasus. The first ICR decision approved the KC-46A’s Centerline Drogue System mission set on July 9. Transportation Command can now task the KC-46 for the C-17, the B-52H, and the KC-46 receivers. This is the first ICR decision regarding the air refueling boom mission set. As a result, the Pegasus aircraft and crews can now accept operational tasks that would otherwise be filled by KC-135s and KC-10s.

July 15/21: ICR The KC-46A has gotten its first Interim Capability Release (ICR) mission set, the approval to use its Centerline Drogue System. Air Mobility Command commander Gen. Jacqueline Van Ovost gave the greenlight on July 9. The decision provides more daily “taskable” operational capabilities to the various services. “This decision reflects a risk-informed, data-driven, constraint-analyzed approach to releasing KC-46A operational capabilities to the joint force,” Van Ovost was quoted as saying.

June 14/21: Japan A group of 12 Japan Air Self-Defense Force (JASDF) aircrew students have started their training to operate the KC-46 aerial refueling tanker at Altus Air Force Base, Oklahoma. Lead by Lt. Col. Tetsuji Kamiguchi, 405th Air Refueling Squadron commander, the team consists of six pilots and six boom operators. The three-months conversion course is made up of three phases. The academic phase will have four classes daily before they proceed to the second phase to work on simulators and performed pre-briefs and debriefs. The group will then proceed to fly eight flights and a check ride with one of the 56th Air Refueling Squadron instructors before graduating.

 

May 27/21: Development Boeing won a $101.7 million contract modification for KC-46 engineering, manufacturing, and development contract. This modification provides for the exercise of Option Five for interim contractor support and the exercise of the options for logistics service representatives/field service representatives support for Seymour Johnson Air Force Base, North Carolina. Work will take place in Seattle, Washington and Seymour Johnson AFB. Estimated completion date is June 27, 2022.

April 21/21: Japan Boeing won a $79.5 million contract modification for KC-46A long lead spares, initial spares and support equipment. This modification provides mission essential long lead spares, initial spares, and support equipment for use on the Japan KC-46 aircraft being produced under the basic contract. The US Air Force awarded Boeing $279 million for the Japan Air Self-Defense Force’s (JASDF) first KC-46A tanker in December 2017. The agreement was completed through the Foreign Military Sale process between the US government and Japan. Japan is now on contract for a total of four KC-46 tankers. Japanese partners produce 16% of the KC-46 airframe structure. Work under the contract modification will take place in Everett, Washington. Estimated completion date is June 30, 2024.

 

March 15/21: OBIGGS A category 2 deficiency for the KC-46A aerial refueling tanker is prevent pilots from taking off in the tanker until the On-Board Inert Gas Generation System (OBIGGS) countdown timer reaches zero. OBIGGS will fill the fuel tanks with nitrogen to prevent the tanks from exploding if there is residual fuel inside. Maj. Tim McBride, an instructor pilot with the 931st Air Refueling Wing, told Defense News that the system take on average 1.5 hours to be ready. But occasionally, the countdown timer will reset and that increased the waiting time. To fix the issue, the service has decided to amend the flight manual so that the flight crew can now take off even if the OBIGGS is still counting down. This will be implemented next month.
February 23/21: LOA Israel inked a letter of acceptance (LOA) with the United States for the procurement of two Boeing KC-46A Pegasus tanker aircraft, and plans further similar agreements to enhance its qualitative military edge (QME) in the region. According to the Ministry of Defense, the LOA for the tankers was signed over the previous weekend. It added that it intends to enter into similar agreements for the standing up of a third squadron of Lockheed Martin F-35I Adir combat aircraft, the replacement of its Sikorsky CH-53D Yasur heavy-lift helicopters, the procurement of advanced munitions, “and more”.
February 17/21: Israel The Israeli ministerial committee for military acquisitions signed off on the purchase of another squadron’s worth of F-35 fighter jets, as well as four Boeing KC-46 refueling planes and advanced missiles and bombs on Tuesday, following government approval last week for a contentious funding scheme to pay for the equipment involving massive loans from the United States, the government said.
January 22/21: G081 Boeing won a $2 billion contract modification for Lot 7 production KC-46 aircraft, subscriptions and licenses and G081 flat file. The modification provides for the exercise of an option for an additional quantity of 15 KC-46 aircraft, data, subscriptions and licenses, and G081 flat file being produced under the basic contract. The company delivered the first KC-46A to the Air Force in January 2019. Since then, Boeing has delivered 42 tankers to four different bases. The next-generation KC-46 brings new capabilities and operational flexibility to the US Air Force and international customers. Boeing says the KC-46 is a multirole tanker designed to refuel allied and coalition military aircraft compatible with international aerial refueling procedures. It’s also equipped to carry passengers, cargo and patients on any mission at any time. Work will take place in Seattle, Washington and is expected to be finished by May 31, 2024.
January 14/21: Deal For 12 Boeing won a $1.7 billion contract modification for Lot Six production of KC-46 aircraft, subscriptions and licenses, and G081 flat file. The contract modification provides for the exercise of an option for an additional quantity of 12 KC-46 aircraft, data, subscriptions and licenses, and G081 flat file being produced under the basic contract. According to Boeing, this is the sixth production lot of the tankers and is designed to bring new capabilities and operational flexibility to the Air Force and other customers. The KC-46 is a multirole tanker, designed to refuel allied and coalition military aircraft compatible with international aerial refueling procedures. It is also equipped to carry passengers, cargo and patients. Work will take place in Seattle, Washington. Estimated completion is in April 30, 2023.
December 23/20: Liquid Palletized Systems Meggitt Defense Systems won a $27.4 million contract modification, which adds scope for the procurement of additional P-8A liquid palletized systems in ordering Years Two, Three and Four, with 10 units in Year Two, 11 units in Year Three and 11 units in Year Four, in support of the Navy P-8A aircraft. The P-8A Poseidon is the US Navy’s maritime patrol aircraft. It is capable of broad-area, maritime and littoral operations, and is also successful at search and rescue. Operating with a smaller crew, yet delivering an extended global reach, greater payload capacity, higher operating altitude, open-systems architecture and significant growth potential, the P-8A provides more combat capability. Work will take place in California, Washington and New York. Estimated completion will be in November 2024.
December 18/20: Military Unique Program Boeing won a $41.7 million delivery order for consumable and depot-level repairable parts for the KC-46 military unique program. The Boeing KC-46 Pegasus is a military aerial refueling and strategic military transport aircraft. In 2011, the DOD announced the Boeing Company as the winner of a competition to build 179 new KC-46 Aerial refueling tankers for the Air Force, a contract valued at roughly $35 billion. Boeing designed the KC-46 to carry passengers, cargo and patients. The aircraft can detect, avoid, defeat and survive threats using multiple layers of protection, which will enable it to operate safely in medium-threat environments. Work will take place in Missouri. Estimated completion date is December 15, 2023.
December 9/20: Interim Enhancements The US Air Force is to field interim enhancements to the problematic Remote Vision System (RVS) for its Boeing KC-46A Pegasus tanker-transport aircraft. The Air Force Materiel Command (AFMC) announced the move, saying that demonstration flights conducted over the summer (third quarter) had validated the Enhanced Remote Vision System (ERVS) as a stopgap measure until RVS 2.0 is rolled out in late 2023. RVS 2.0 is the agreed final solution to resolve Category 1 deficiencies associated with the current RVS. “The implementation of ERVS will provide some benefit to our ‘Total Force’ boom operators in the near-term, but most importantly will not delay the fielding of RVS 2.0,” General Jacqueline Van Ovost, commander of Air Mobility Command (AMC), was quoted as saying.
November 5/20: KC-Y The United States Air Force is reportedly ready to move forward with the second program aimed at renewing its fleet of aerial refuelers, formerly known under the codename KC-Y. Head of Air Mobility Command Gen. Jacqueline D. Van Ovost indicated that the service will be moving forward with the bridge tanker KC-Y acquisition program. The competition will be full and open plus “non-developmental“, meaning it will be based on an existing, proven aircraft, according to an Air Mobility Command spokesperson. The Air Force is defining which capabilities it needs in its next tanker and how it will “immediately follow the existing KC-46A delivery timeline,” she said. KC-Y will replace the KC-135 and bridge the capability gap between the KC-46 and the future tanker KC-Z. The KC-46 Pegasus was due to be withdrawn by 2025. But the development of the tanker exceeded the initial forecast by $3 billion. The aircraft has also encountered numerous technical problems since its delivery.
October 9/20: Commercial Common Program Boeing won a maximum $149.6 million delivery order for the KC-46 Commercial Common Program consumable parts. The KC-46 Pegasus is a military refueling and strategic military transport aircraft. The Air Force intends to procure 179 Pegasus aircraft by 2027. The first four KC-46 aircraft were delivered to McConnell AFB, KS, in January 2019. The KC-46A places the boom operator on the flight deck, viewing receivers through a camera-driven display called the Remote Vision System (RVS). Work will take place in Missouri. Estimated completion date is October 7, 2023.
September 30/20: Engineering Boeing won a $40 million contract modification for KC-46 engineering, manufacturing, and development. This provides for qualification test of the components and full life qualification of the actuator, as well as for conducting lab test, ground test and flight test verifications. The KC-46A Aerial Refuelling Aircraft has a maximum fuel capacity of 212,000lb. The aircraft is fitted with a flush-mounted air-to-air refuelling receptacle capable of accepting fuel at 1,200gal/min. The tanker is capable of carrying 18 cargo pallets, as well as transporting 58 passengers normally and up to 114 passengers during contingency operations. The tanker aircraft also provides urgent aeromedical evacuation by transporting 54 medical patients. The maximum takeoff weight of the tanker aircraft will be 415,000lb (188,241kg). Work will take place in Seattle, and is expected to be completed December 31, 2023
September 9/20: eRVS US Air Mobility Command commander, Gen. Jacqueline Van Ovost, made her first visit to Boeing Field, Tukwila, Washington, on September 4 to receive briefings with Boeing officials. It was disclosed that Boeing took the opportunity to demonstrate a potential interim Enhanced Remote Vision System (eRVS) to Van Ovost during the visit. Boeing is working on RVS 2.0 to fix the troubled system currently installed on KC-46A fleet. The deficiencies of the system in its current form has forced the air force to place operational restrictions on KC-46 refueling. RVS 2.0 will include 4K color cameras with proper viewing geometry, operator stations with larger screens, a laser ranger for refueling aircraft distance measurement and boom assistance augmented reality.
May 25/20: Senators Call for KC-46 Delay Investigation Three US senators called on the Government Accountability Office on May 22 to investigate delays keeping the KC-46 military aircraft from use in missions. In a letter James Lankford, Janne Shaheen, and Maggie Hassan demanded “periodic assessments” of the progress made by builder Boeing to fix longstanding problems of the cargo and refueling plane, notably its refueling boom and its rearward-facing remote vision system. In addition, the plane was prone to cargo locks becoming unlocked while mid-flight. Also, inspections have found tools, rubbish, leftover parts and loose fittings in planes delivered by Boeing since January 2019.
April 6/20: MoA The US Air Force has come to an agreement with Boeing for the final KC-46A Pegasus Remote Vision System design. Two agreements were reached on April 2 to be incorporated in the KC-46 contract. The first Memorandum of Agreement institutes the redesign and retrofit of RVS 2.0 in full compliance with the contract requirements at no additional cost to the government. This agreement addresses deficiencies that hindered safe and effective refueling operations. The other agreement is to previously withheld contract payments to help Boeing counter Covid-19 impacts. This amount is worth $882 million for 33 KC-46s delivered so far. Within 120 days, the Air Force and Boeing will conduct an expedited process to determine final specification compliance or non-compliance.
March 25/20: Simulator Training The FlightSafety Services on a $25 million contract for a multi-country KC-46 aircrew and maintenance simulator training. The contractor will provide KC-46 aircrew and maintenance training to support the U.S. government and Air Force Security Assistance Training international partners’ mission objectives. The KC-46 is built as an empty 767 airframe in Everett, Wash., then transferred to the south end of Paine Field, called the Military Delivery Center. The jet’s military systems, including the refueling and communications equipment, are installed there. The KC-46 Pegasus is a wide body, multi-role tanker that is capable of carrying a fuel capacity of 212,000 pounds. Work will take place at Altus Air Force Base, Oklahoma. Estimated completion will be in September 2026.
March 6/20: Engineering, Manufacturing And Development Boeing won a $36.7 million contract modification or KC-46 engineering, manufacturing and development contract. The modification is for the component build and development of the hardware system integration lab to conduct lab verification and ground test verification for the boom telescope actuator redesign. The KC-46A Pegasus is a widebody, multirole tanker that can refuel all US, allied and coalition military aircraft compatible with international aerial refueling procedures. Problems with the boom were among the issues that the Air Force and Boeing knew still needed to be resolved at the time the tankers first began being delivered early last year. work will take place in Seattle. Estimated completion will be in February 2023.
March 5/20: Israel The DoS approved a possible Foreign Military Sale to Israel of up to eight KC-46 aircraft and related equipment for an estimated cost of $2.4 billion. The KC-46A is a 767-2C provisioned freighter with a 767-400 flight deck (this flight deck features the Rockwell Collins large format displays of the 787 airliner). The KC-46A has a minimum crew of three comprised of a pilot, co-pilot, and mission system operator/officer. It can carry 96 tonnes of fuel, although it should be noted that the KC-46A loses much of its underfloor cargo space with auxiliary tanks in doing so. According to the DoS, the proposed sale supports the foreign policy and national security of the United States by allowing Israel to provide a redundant capability to US assets within the region, potentially freeing US assets for use elsewhere during times of war.
March 2/20: Aircrew Trainings System FlightSafety won a $33.2 million not-to-exceed modification for the exercise of the KC-46 Aircrew Training System production year 5 options. The contract modification is for the exercise of option contract line item numbers for two additional weapon system trainers, two boom operator trainers, fuselage trainer, fuselage trainer sprinkler system and installation, two pilot part task trainers, boom operator part task trainer, additional learning management workstations, fuselage trainer support equipment, McGuire and Altus Site Activations, systems engineering and program management, Visual Database Airfield Models and new refresher training scenarios. The KC-46 Pegasus is a wide body, multi-role tanker. It is capable of carrying a fuel capacity of 212,000 pounds. Work will take place in Broken Arrow, Oklahoma. Estimated completion will be by February 2022.
January 31/20: Leasing? The Pentagon is considering leasing aerial refueling tankers to mitigate Boeing KC-46A Pegasus tanker delivery delays to the US Air Force. General Stephen Lyons said hat the aerial refueling force element across the command is the most stressed. USTRANSCOM is a unified, functional combatant command that provides globally integrated mobility operations and support to the 10 other US combatant commands and military services. An advantage of leasing tanker capability, he said, would be immediately relieving tanker pressure as the USAF continues to retire Boeing KC-135 Stratotankers and McDonnell Douglas KC-10 Extenders. But Gen Lyons said a disadvantage would be that these leased tankers could not be used in contested or combat environments. Gen Lyons is specifically concerned that the continuing retirement of legacy tankers, combined with insufficient KC-46s, would result in a significant decrease of “taskable tails.” Douglas Birkey, executive director of the Air Force Association’s Mitchell Institute for Airpower Studies, told Jane’s on 29 January that these are aircraft that can be tasked by the tanker airlift control centre at Scott Air Force Base in Illinois to perform mission requirements.
December 26/19: Cybersecurity Flightsafety Services won an $11.8 million contract modification for support of the KC-46 Aircrew Training System. The contract modification provides for the exercise of calendar year 2020 operation and sustainment and cybersecurity efforts. The KC-46A Aerial Refueling Aircraft, based on the KC-767 refueling aircraft. The contract for KC-46 tankers was awarded to Boeing in February 2011. The company announced the major suppliers to be involved in the project in June 2011 and the Integrated Baseline Review (IBR) for the program was completed in August the same year. Last month the Pegasus completed the first flight around the world last month in a seven-leg trip. The Boeing aircraft is undergoing initial operational testing and evaluation to test its capabilities and effectiveness even as the Air Force flagged concerns with certain issues identified during the inspection, including a problem with the cargo locks. Flightsafety will perform work until December 31, 2020.
November 14/19: Retrofit The US Air Force has reportedly approved a retrofit to prevent cargo locks on an aerial refueling tanker from coming undone midflight. Will Roper, the Air Force’s top acquisition official, told Defense News he’s confident the KC-46A Pegasus aerial refueling tanker’s malfunctioning cargo locks will be fixed within months. In September, after a flight where cargo locks on the bottom of the aircraft’s floor became unlocked midflight, the tanker was restricted from carrying either cargo or people in the back of the aircraft. So far Boeing has paid more than $3.5 billion of its own money to fund corrections to ongoing technical issues, of which the cargo issue is the fourth. The company has also paid to address the tanker’s remote vision system, which provides imagery that in certain lighting conditions looks warped or misleading; instances of the boom scraping against the airframe of the receiver aircraft; and a requirement to redesign the boom to accommodate the A-10 plane.
September 30/19: Lot 5 Production Boeing won a $2.6 billion contract modification for Lot 5 production KC-46 aircraft, initial spares, and support equipment. The deal provides for the exercise of an option for an additional quantity of 15 KC-46 aircraft, data, two spare engines, five wing refueling pod kits, initial spares, support equipment, subscriptions and licenses, and G081 flat file being produced under the basic contract. The KC-46A Pegasus is a widebody, multirole tanker that can refuel all US, allied and coalition military aircraft compatible with international aerial refueling procedures. The aircraft is capable of carrying 212,299 pounds of fuel and 61,000 pounds of cargo, 10 percent more than the KC-135 can hold. The KC-46A is equipped with a refueling boom driven by a fly-by-wire control system, and is capable of fuel offload rates required for large aircraft. Its hose and drogue system adds additional mission capability that is independently operable from the refueling boom system. Work will take place in Seattle, Washington, and is expected to be completed by March 2023.
August 13/19: Pease Guard Base First to Receive Pegasus The Pease Air National Guard Base in New Hampshire is the first guard base to receive a next-generation KC-46A Pegasus refueling tanker plane. The refueling tanker flew into the Pease Air National Guard base late Thursday afternoon. The Pegasus is developed from a Boeing 767 passenger plane. It is replacing KC-135 Stratotankers in the US Air Force fleet of refueling planes. The Air Base will receive three KC-46As per month for four months. The KC-46A can refuel any fixed-wing plane, foreign or domestic made, while both planes are airborne. It can also accommodate a mix of passengers, including patients and cargo. Boeing had been three years behind schedule on the Pegasus program before deliveries began. The Air Force halted deliveries a couple of times due to debris in the plane. Last week, Lockheed received a $55.5 million contract modification for engineering work on a redesign of the plane’s boom telescope actuator.
August 6/19: Engineering, Manufacturing and Development The Air Force awarded Boeing a $55.5 million contract modification for KC-46 engineering, manufacturing and development. The Boeing KC-46 Pegasus is a military aerial refueling and strategic military transport aircraft developed by Boeing from its 767 jet airliner. The new KC-46 fleet is planned to replace the US Air Force’s aging fleet of Boeing KC-135 Stratotankers. In April 2019, the company was awarded a $5.7 billion contract for a new fleet of the aircraft with combat capabilities. The KC-46 has completed receiver certification testing with Lockheed Martin F-35 Lightning II fighter aircraft this year. The San Antonio Express News reports that the KC-46 „has been plagued by critical deficiencies that include the plane’s ability to refuel stealth aircraft without damaging them“. The Air Force even stopped accepting the KC-46 twice after debris was found in the planes. These issues have cost the USAF more than $300 million and forced it to limit some refueling operations. Under the current modification, Boeing will perform work in Seattle through February 2021.
June 20/19: Loose Never Ends FlightGlobal reports that the US Air Force is still finding foreign object debris insight KC-46 Pegasus refueling tankers. Tools, rubbish and left-over parts, including loose nuts, are being found since Boeing first delivered the refuelers in January and revamped its inspection process. Assistant secretary of the Air Force, Will Roper cited „cultural issues“ as the root of the problem. Air Force stopped accepting the planes from Boeing in February until its inspection process was changed. Deliveries resumed in March and were halted again after the Air Force found more debris. Will Roper says, he expects all of the KC-46s are going to have foreign object debris.
May 1/19: PC2 Boeing won $5.7 billion for Pegasus Combat Capability (PC2) enhancements. According to the DoD, work will include a broad range of post-production related non-recurring and recurring requirements centered on KC-46 air vehicle needs. The Pegasus KC-46 is a refueling tanker that was developed from the Boeing 767 jet. Boeing was first contracted to build four KC-46A aircraft under the $3.9 billion KC-X contract awarded by the USAF in 2011. The Air Force took delivery of the first two Pegasus aircraft in January this year. However, in March debris issues occurred and acceptance was stopped. Deliveries were resumed last week. Boeing will perform PC2 work in Seattle and the scheduled completion date is April 28, 2029.
April 29/19: Israeli Letter of Request The Israeli Air Force is authorized to issue a Letter of Request for two Boeing KC-46 refueling tankers, IsraelDefense reports. After a new government has been established and the next Minister of Defense has been appointed, the Israeli Air Force will likely face some changes. The most pressing decision to make is what heavy-lift helicopter will replace the CH-53 Yas’ur. In the matter of choosing a new refueling tanker, it is very likely that IAF will decide on the KC-46 as it already has reviewed the aircraft and flown in it. The KC-46 Pegasus was developed by Boeing from its 767 jet airliner.
April 4/19: Halted once more! The Air Force reportedly halted deliveries of the KC-46 Pegasus tanker once again. The reason for the halt are foreign objects in closed compartments. Just last month the Air Force first stopped deliveries for the same reason. Deliveries resumed several days later after Boeing agreed to an additional inspections plan. The decision to stop the Pegasus delivery once more was made on March 23, but this week inspectors kept identifying additional foreign object debris and other areas, in which Boeing did not meet quality standards. Boeing has so far delivered seven KC-46s to the Air Force. The Pegasus is a widebody, multirole tanker, that is able to refuel allied and coalition military aircraft compatible with international aerial refueling procedures.
March 14/19: Air Force resumes Deilvery The US Air Force received a KC-46 Pegasus on March 11 after the aircraft passed a Foreign Object Debris inspection at Boeing’s production facility. The Pegasus is a military aerial refueling aircraft developed by Boeing. The Air Force selected the Pegasus to replace the KC-135 Stratotankers. The first Pegasus was scheduled to be delivered in August 2017 but was delayed until January 2019. Deliveries of the jets were halted last month after foreign object debris was found in one of the aircraft. Boeing had offered to inspect all the aircraft that were accepted by the Air Force. Loose tools and other items were found inside a completed airplane. Subsequent deliveries will occur as Boeing successfully completes each aircraft’s inspections and actions assigned from the review. Boeing plans to deliver 36 of the aircraft this year and about a dozen more are nearing completion.

December 10/18: Japan Japan is ordering a second KC-46A Pegasus for its air force. The aircraft is procured under a contract modification valued at $159 million. Delivery of the first tanker to the JASDF is scheduled for February 2021. Once delivered, the KC-46 will add a significant boost external link to Japan’s aerial refueling capabilities, adding to the current fleet of four KC-767J tankers. Work will be performed at Boeing’s factory in Seattle, Washington and is expected to be completed by June 30, 2021.

December 6/18: KC-46 Phase II certification Boeing achieves another milestone in its KC-46 tanker program and sets the stage for the start of Initial Operational Test & Evaluation testing next year. The Pegasus successfully achieved its Phase II receiver certification, and proved that it can refuel F-16, KC-135, C-17, A-10, KC-46, B-52, and F/A-18 aircraft. Phase II consisted of three weeks of flights with F-15E fighter jets stationed at Edwards AFB in California. Boeing says in a press statement, that during the tests a KC-46 and receiver aircraft flew at different airspeeds, altitudes and configurations to ensure compatibility and performance throughout the refueling envelope of each receiver. “The Air Force crews were with us every step of the way during this critical testing,” said Jake Kwasnik, KC-46 test program manager. “It was awesome to see everyone working together as we conducted flights out of Boeing Field and also at Edwards and Minot Air Force bases.” Phase III receiver testing will start in 2019, and includes training with additional receiver aircraft. Boeing is currently on contract for the first 52 of an expected 179 tankers for the US Air Force.

November 5/18: Refueling qualification Boeing’s new KC-46 tanker receives more certifications as it successfully completes aerial refueling of two additional aircraft types. During recently held tests the KC-46 completed receiver certification testing for the B-52 bomber and the F/A-18 fighter jet, with the F-15 to follow next year. A Boeing spokesperson says that the certification test are in preparation for the start of Initial Operational Test and Evaluation work next year. KC-46A is a militarised version of the 767-2C. Modification include aerial refueling equipment, an air refueling operator’s station that includes panoramic 3-dimensional displays, and threat detection/ countermeasures systems. Boeing recently missed the delivery schedule for its first aircraft which was expected to take place on October 27. The KC-46 acquisition program sees for the delivery of 179 tankers at a cost of $44.3 billion, with the first aircraft expected to be delivered between April and June 2016.

October 19/18: Boeing misses deadline – again! Boeing will miss the delivery deadline of its first KC-46 tanker aircraft to the US Air Force, which was set for October 27th. US Air Force Secretary Heather Wilson told journalists in a round-table at Bloomberg headquarters in New York, that the service and the company are currently trying “to lay down the path forward for delivery and to make sure the deficiencies that have been identified are taken care of in a way that brings that aircraft in as promised.” The missed deadline is the latest in a series of missed deadlines, that include unresolved deficiencies with the tanker’s system for midair refueling and a delayed FAA certification. The KC-46 acquisition program sees for the delivery of 179 tankers at a cost of $44.3 billion, with the first aircraft expected to be delivered between April and June 2016.

September 12/18: More orders The US Air Force is ordering 18 additional KC-46A tanker aircraft from Boeing. The contract has a value of $2.8 billion and includes spares and support equipment for the Lot 4 aircraft. The KC-46A is a wide-body, multi-mission aircraft capable of transporting fuel, cargo, passengers and patients. The airframe is based on the KC-767 but comes with modifications like a cargo door, an advanced flight deck display and militarised modification ranging from an air refuelling operator station to threat detection and avoidance systems. Work will be performed at Boeing’s facility in Seattle, Washington and is expected to be completed by January 2022.

August 8/18: Competition Israel Aerospace Industries (IAI) and Boeing are currently competing in being the lead vendor in one of Israel’s biggest defense procurement programs. The Israel Air Force is looking to modernize its fleet of tanker aircraft as means to maintain its air-superiority. IAI proposed to buy buying used Boeing 767 aircraft on the open market and converting them for airborne refueling of combat planes, however Boeing is reluctant to grant IAI permits to convert its planes to tanker configuration. Boeing has a clear interest in ousting IAI from the procurement program as it wants to push sales of its newly developed KC-46, which comes with a price-tag of $250-300 million. The Israel Air Force’s current tankers are used Boeing 707s converted by IAI in the early 1980s.

May 08/18: Can the KC-46 be delivered in time? Boeing’s KC-46 Tanker program hit another bump. Due to continuous cost overruns and schedule delays, the company has racked up more than $3 billion worth of pretax charges. Just last week Boeing disclosed another $81 million-pretax penalty on the program in its financial report for the first quarter of 2018. According to the terms of Boeing’s fixed-price development contract with the US Air Force, the company is responsible for any costs over the $4.9 billion award. Air Force Secretary Heather Wilson has been publicly dismissive of the company’s progress, telling lawmakers that the company has perhaps been too focused on its lucrative commercial business to give the tanker program the attention it deserves. In total, Boeing has 34 KC-46s in some stage of production, and the first four aircraft planned for delivery have already flown and are in storage. Despite company officials reassuring that all ‘required assets available’ obligations can be met, it is yet unclear if Boeing will be able to deliver all of the 18 certified KC-46s and nine refueling pods this year.

April 30/18: More delivery delays A new assessment carried out by the US Government Accountability Office (GAO) has found that Boeing will be unable to deliver all 18 KC-46 Pegasus aerial refueling tankers this year and will only be able to do so in May 2019. Speaking on the new timeline after a visit to Boeing’s Seattle facility in March, Air Force Under Secretary Matt Donovan said the firm “were very pressurized to get this the last ten yards” to delivery, adding that first delivery “is not a contractual requirement,” and the original goal of April to June 2016 “was always an estimate.” Still, it’s “a psychological milestone, and it’s important to us.” He added that he had also seen software fixes that “will vastly improve” the refueling operations.

April 9/18: Milestone in the face of delays Boeing has scored another milestone in its KC-46 Pegasus tanker program, several weeks after Secretary of the Air Force Heather Wilson criticised the firm for delays to the program. The announcement made by Boeing on Wednesday said that the Pegasus completed the fuel on-load testing portion required for the FAA Supplemental Type Certificate (STC) by refueling another KC-46A in mid-air. The fuel transfer took place during a 3h, 40min-long flight on an undisclosed date, successfully transferring 66,200kg (146,000lb) of jet fuel and achieved the maximum fuel off-load rate of 1,200 gallons per minute. The KC-46 now has demonstrated the ability to receive fuel from three tankers in the USAF fleet: KC-46, KC-135 and KC-10 aircraft, Boeing says. It also has demonstrated refueling with other aircraft including the F-16, F/A-19, AV-8B, C-17 and A-10.

March 22/18: Wilson slams delays Boeing’s KC-46 Pegasus tanker program has come under fire after Secretary of the Air Force Heather Wilson took the firm to task during a House Armed Services Committee hearing on Tuesday, Flight Global reports. During the hearing, Wilson criticised the airframer over delivery delays of the aircraft to the USAF saying: “One of the frustrations with Boeing is they are much more focused on their commercial activity then getting this right for the Air Force, and getting these aircraft to the Air Force.” “We have asked them to get their A team on this to get these problems fixed and get the aircraft to the Air Force,” she added. The firm responded by saying that “there is no greater priority at The Boeing Company right now than the delivery of the KC-46,” however, did not guarantee that the first batch of tankers would be delivered by the second quarter of 2018. The USAF awarded Boeing a $4.9 billion contract in 2011 to modify the 767-2C commercial freighter into the KC-46A military tanker, but manufacturing and development issues have caused the firm to reportedly lose $2 billion.

March 2/18: EPT Testing Following a report released in January expressing concerns about the KC-46 Pegasus tanker aircraft, the US Air Force is working with the Pentagon’s operational test and evaluation office to dissuade these issues while maintaining the aircraft will keep to its milestones and schedules. One issue raised was that the aircraft did not meet the office’s standards for electromagnetic pulse testing—which took place in July at Naval Air Station Patuxent River, Maryland, and Edwards Air Force Base, California—however, this was because not all of the systems were online during the previous round of tests. The test showed that the tanker’s flight-critical and boom-refueling systems could withstand a 6-decibel electromagnetic pulse, but certain systems were uninstalled or deactivated before testing, according to the report. “The systems that were uninstalled or deactivated were not flight critical or required for aerial refueling operations,” the command said. There are no plans as of yet for additional EPTs.

December 27/17: FMS Contract-Japan Work is to begin on producing Japan’s first KC-46 tanker aircraft, following the $289 million USAF firm-fixed-price contract awarded to Boeing to deliver one unit to Tokyo. The contract provides for non-recurring engineering, integrated logistics support and one KC-46A aircraft and is a 100 percent foreign military sale (FMS) to the Japanese government. Work will take place in Seattle, Washington with delivery to the JASDF to take place by February 28, 2021. Once delivered, the KC-46 will add a significant boost to Japan’s aerial refueling capabilities, adding to the current fleet of four KC-767J tankers.

December 8/17: Milestone-First Flight Despite announcing delays to its delivery schedule on Tuesday, good news rocked the KC-46A Pegasus Tanker program as the first operational aircraft successfully carried out its maiden flight on the same day. Over the course of the 3.5 hour flight, test pilots took the tanker to 39,000 feet and performed operational checks on its systems before landing. The model used in the test is the seventh built for the program, with the previous models used for certification and testing and to date have racked up 2,200 flight hours and more than 1,600 “contacts” during refueling flights with F-16, F/A-18, AV-8B, C-17, A-10, KC-10 and KC-46 aircraft.

December 6/17: Delivery Delays Boeing has admitted that the planned delivery of the first KC-46 Pegasus tanker aircraft to the US Air Force (USAF) has been postponed. The firm had previously maintained, as recently as last month, that it was confident the tanker could be delivered by the end of the year, after missing the initial delivery deadline of August 2017. Now, Boeing say deliveries will now take place in 2018, and is contractually obliged to deliver 18 KC-46s and nine refueling pods by October 2018—14 months later than originally planned. Cost overruns for the program experienced by Boeing to date amount to approximately $2.9 billion pretax, or $1.9 billion after tax.

November 16/17: Despite testing issues and delivery delays, Boeing has been aggressively marketing its new KC-46A tanker aircraft to Middle East governments at this year’s Dubai Airshow. There is a high demand for aerial tankers in the region as the US Air Force’s (USAF) tanker fleet supports the Saudi Arabian-led aerial campaign in Yemen with air refuelling, and the airshow is being used by Boeing as an opportunity to get governments to augment their tanker capabilities or switch allegiances. But the US airframer will have its work cut out for them—rival Airbus has recently delivered its A330 tanker to Saudi Arabia, the United Arab Emirates and Kuwait.

November 1/17: Early test data gathered by the US Air Force (USAF) has led the service to be confident that a software solution could fix some deficiencies found in the Boeing KC-46 tanker aircraft. Speaking on the testing, Gen Carlton Everhart, commander of the USAF Air Mobility Command, said the reprograming could fix a high-frequency (HF) transmit as well as an “uncommanded boom extension”, although further testing will be required. The HF radio, which must be turned off to avoid electrical sparking between the boom and receiver, is now tolerable according to vendors, while the boom extension issue does not damage the aircraft.

October 16/17: A Boeing and US Air Force (USAF) test team has successfully completed the first mid-air refueling involving two KC-46A aerial tankers. The demonstration took place during a recent four-hour flight, during which the two aircraft transferred 38,100 pounds of fuel to each other at 1,200 gallons of fuel per minute. Manufacturer Boeing hailed the demonstration as a “milestone” that opens the door to additional certification and specification compliance testing. More than a dozen KC-46s will be delivered to the USAF next year and will begin replacing the service’s ageing fleet of KC-135s. So far, KC-46 test aircraft have had more than 1,300 contacts during refueling flights with a number of aircraft, including the F-16, F/A-18, AV-8B, C-17, A-10 and KC-10.

September 26/17: The US Air Force (USAF) has expressed concern that Boeing will face difficulties in meeting a contractual obligation to deliver 18 KC-46 tankers to the service on time. Testing conducted in 2016 found a series of “category one” deficiencies, including where its boom scraped the surface of the aircraft being refueled. The testing also found that the tanker is not detecting when it is missing the receptacle, making it impossible for a KC-46 pilot to communicate that the receiving aircraft has potentially been damaged, the USAF said. While the USAF still believes that Boeing will fix these deficiencies in time to deliver the first KC-46 in late spring of 2018 (with a contractually mandated “required assets available” deadline for 18 tankers following in October), the service did not commit to accepting the aircraft from Boeing if the problem was not fixed, and at this point the timeline for resolving the issue is yet to be determined.

September 21/17: The head of the USAF’s Air Mobility Command has revealed that deliveries of the KC-46A tanker from Boeing will likely take place next year, and it remains unknown whether the firm will meet the “required assets available” milestone scheduled for October 2018. Speaking at the annual Air, Space and Cyber conference near Washington DC, Gen Carlton Everhart said that the service had discovered severe flaws on the tanker, known as “category 1 deficiencies”. Among the most glaring, the tip of its boom has on occasion struck receiver aircraft outside their refuelling slipways. Unless Boeing resolve the issue quickly it could delay a scheduled 1 December delivery.

September 14/17: Boeing expects to deliver its KC-46A tanker to the US Air Force by December, but the service branch expects that this schedule will slip into spring 2018. Brig. Gen. Donna Shipton, Tankers Directorate program executive officer said that the manufacturer has made “steady progress, just slower than planned” to complete Federal Aviation Administration certifications and flight tests. In recent months, Boeing had projected first deliveries in March and later August of this year before its most recent target date of December. The USAF plans to buy 179 KC-46 tankers through 2027. Eventually, the service branch expects to replace 455 aging KC-135 Stratotankers and KC-10 Extender tankers in the fleet.

July 31/17: Electromagnetic testing of the KC-46A Pegasus tanker has been completed by a joint team involving Boeing, the USAF, and the Naval Air Systems command, moving the aircraft closer to its first delivery. Testing took place at Naval Air Station Patuxent, Md. electromagnetic pulse laboratory and the Benefield Anechoic Facility at Edwards Air Force Base, Calif, which aimed to assess whether the aircraft could safely operate when confronted by the electromagnetic fields generated by equipment like radar. A Government Accountability Office (GAO) report in March had deemed the tests as one of the two key risk factors that could keep Boeing from meeting its delivery goals. However, Boeing has stated that the timing of the electromagnetic tests would not push back other key milestones and that the company still intends to deliver the first KC-46A this year.

June 12/17: Delivery of KC-46A tanker aircraft to the USAF has been pushed back until Spring 2018,according to service officials.Manufacturer Boeing had initially scheduled the first deliveries for this September, but this has now been pushed back while the manufacturer acquires airworthiness certifications and complete a flight test program for the plane. The delay is not expected to add addition costs to the taxpayer.

June 2/17: A KC-46 Pegasus tanker aircraft has entered the Benefield Anechoic Facility (BAF) at Edwards Air Force Base to undergo testing. The tests in question are integral in order to demonstrate that the tanker meets Federal Aviation Administration certification requirements and Defense Department electromagnetic environmental effects requirements for systems. These tests include shielding effectiveness, emission control and high intensity radiated fields. The BAF is the largest anechoic chamber in the world, and provides a location where electronic warfare tests can be conducted without radio frequency interference from the outside world.

May 5/17: Boeing has reached an important milestone external link in bringing its KC-46 tanker programcloser to serial production, announcing that it now has has a total of six units ready for its testing program. The newest, of the planes, which is the second to be produced under a low-rate production order, conducted its first test flight on April 26, and future testing will be largely focus on ensuring that the tanker can stand up to electromagnetic fields—radars and powerful radio towers are capable of scrambling aircraft electronic systems if they are not carefully shielded. Boeing intends to eventually produce as many as 179 KC-46 tankers for the USAF.

March 29/17: Boeing has received a $59 million contract modification to continue production for the USAF’s KC-46 tanker aircraft. The deal will see the company provide interim contracting support, a temporary service conducted in lieu of organic capability for a predetermined time. The deal allows Boeing to defer investment in all or part of required support resources. Work is expected to be complete by March, 2018.

February 23/17: Boeing is taking some suppliers to court after they sold mislabeled chemicals that caused the maiden flight of the KC-46 tanker to be delayed by a month. Able Aerospace Adhesives and AlfaKleen Chemical Labs, both from California, are being sued in the sum of $10 million or more for the mix up, whose incorrect chemical damaged components in the jet’s refueling system, and time was lost by Boeing in order to to replace those damaged parts. The liquid provided was certified to meet MIL-PRF-680 Type III certification; it was, however, actually more acidic than required.

January 30/17: Boeing has won a $2.1 billion contract for the provision of 15 KC-46 aerial refueling aircraft to the US Air Force. The contract, awarded on Friday, is in addition to the initial $4.2 billion contract awarded by the USAF to develop and test the aircraft, and an earlier $2.8 billion award for 19 planes. So far, the fixed-price contract has incurred cost-over runs of $2.4 billion, including a recent $201 million after-tax charge that Boeing announced on Wednesday.

January 26/17: It seems likely that the KC-46A aerial tanker will not meet its aggressive delivery schedule, with manufacturer Boeing stalling deliveries to the USAF until late 2017. Boeing had already moved its delivery schedule from March to August. The revelations were found in an annual report by the DoD’s Director of Operational Test & Evaluation, which stated “execution of the current schedule assumes historically unrealistic test aircraft fly and re-fly rates.”

November 18/16: Boeing is eager to sell its KC-46A aerial refueling tanker to India. The Indian Air Force has yet to procure a capability to refuel its C-17 and P-8I aircraft, and New Delhi has eyed up the Pegasus to fill such a role. A laborious search has been underway to fill a six multi-role tanker capability soon to be vacated by their aging IL-76 aircraft. Earlier attempts to procure Airbus A 330 MRTT never came to fruition.

September 23/16: The US State Department has cleared the sale of four KC-46A aerial refueling tankers to Japan in what is estimated to be a $1.9 billion deal. All aircraft will come equipped with Northrop Grumman’s AN/AAQ-24(V) Large Aircraft Infrared Countermeasures (LAIRCM) system. Tokyo first announced its intention to purchase the new tankers last October, with the recent approval from the Pentagon moving it closer to becoming the aircraft’s first foreign customer for manufacturer Boeing.

September 22/16: Gen. Carlton Everhart, head of the mobility command of the USAF has said that the number of KC-46 tankers the service is set to procure by 2028 are not enough. 179 units of Boeing’s latest tanker will be delivered; however between 2028 and 2035, no KC-46s are scheduled for delivery, leaving a capability gap. To remedy the issue, Everhart suggested that the flying branch embark on a study this year for a new KC-Z aerial refueling tanker that will enter service in 2035, as well as looking into the possibility of developing a “KC-Y” tanker to fill the procurement gap.

August 22/16: Last week ended on an extremely good note for both Boeing and Lockheed Martin after the companies were awarded major multi-billion contracts by the USAF. For Boeing, an impressive $2.8 billion award was granted on Thursday as part of the low rate initial production of the KC-46A following the tanker’s Milestone C decision earlier this month. 19 aircraft will be produced alongside spare parts, engines and refueling pods. However, this was astronomically dwarfed on Friday when Lockheed Martin was handed a $10 billion deal for all future orders of the C-130J Super Hercules production program as well as any foreign military sales for the aircraft.

August 15/16: After a long wait, the KC-46A tanker has been cleared for production. The Milestone C approval was awarded by US Under secretary of defense for acquisition, technology and logistics, Frank Kendall, following a series of stringent refueling tests of various USAF and Navy aircraft. Contracts are expected to be awarded to Boeing within the next 30 days for the first two low rate initial production lots, totaling 19 aircraft.

August 12/16: A long awaited low-rate initial production decision for the KC-46 tanker is to be made by the end of the month. Secretary of the USAF Deborah Lee James informed the media of the upcoming meeting “We believe that the aircraft has met all of the wickets that are required to meet milestone C, but of course that remains to be seen, so I’ll say stay tuned on that.” Flight testing of the aircraft wound up in July following a number of hardware and software fixes to the plane’s boom following aerial refueling problems.

August 9/16: Ground has been broken on the new $44 million KC-46A Pegasus sustainment campus at Tinker Air Force Base in Oklahoma. The facility will be responsible for all the maintenance, repair and overhaul operations required for the tanker. The first KC-46A are expected to roll into Tinker in 2018.

July 25/16: Boeing has announced the latest in an ongoing saga of cost overruns with the company taking a $393 million hit on the KC-46 tanker program. Well published issues such as the fault with the aircraft’s refueling boom have resulted in delays to the aircraft reaching an important program milestone prior to initial production. The charges are to be formally announced on July 27 and brings the total value of penalties to almost $1.9 billion. Don’t worry Boeing, the next round of drinks are on us.

July 20/16: Following the refueling of an A-10 Thunderbolt, the KC-46 has completed the last in a series of in-flight refueling tests necessary before its Milestone C production decision. A selection of Navy, USAF and USMC aircraft were chosen including the C-17, F-16, F/A-18 and AV-8B. The Milestone C decision to begin low-rate initial production is expected in August.

July 15/16: A KC-46A fitted with its brand new modified boom has successfully managed a mid-air refueling of a C-17 with the previous axial loading issues no longer present. The testing was carried out on July 12 and the USAF also refueled an F-16 on July 8. Refueling attempts with the F-16 earlier this year were successful, although a higher than expected axial load on the boom was detected. The higher load was again present during the initial attempt with the C-17 which necessitated installation of hydraulic pressure relief valves in the boom.

July 12/16: “Bypass surgery” has been carried out on the KC-46A to fix problems with the the flying boom on the tanker. A hardware fix has been implemented by adding two bypass valves to lighten the load on the boom. Boeing describing the modification as similar to that used on the US Air Force’s current KC-10 tankers.

June 6/16: Setbacks to the KC-46A tanker program have been compounded as Boeing has admitted that a software solution to fix the load issues on the flying boom was not robust enough and the company will have to modify the hardware itself. The plane was initially aiming to have a low-production order to deliver 18 tankers by next August. Issues arose during refueling trials with larger aircraft such as the C-17 military transporters which caused unacceptable stress loads along the axis of the boom.

May 31/16: Following close on the heals of the F-35’s delay in achieving initial operational capability (IOC), the KC-46A tanker will miss its scheduled Spring 2017 delivery to units. Instead, deliveries have been rescheduled for late summer or early fall of next year. The KC-46 tanker program was already on a tight trialing schedule as part of its Milestone C demonstration in June, but will now be pushed back until August.

May 9/16: Boeing has announced that they have developed a hardware and software fix for the KC-46A aerial tanker, allowing it to pass fuel to C-17 aircraft. The company encountered problems regarding a boom axial load issue during an earlier test to refuel the C-17, causing a setback to the already delayed flight test program. A “milestone C” decision on low rate production by the Pentagon is now expected in June after initially planned for April and now May.

April 29/16: April 29/16: Legislation being considered by the House Armed Services Committee (HASC) could see the last external link of the USAF’s F-117A Nighthawk fleet sent to the scrap yard. Retired since 2007, a fleet of the pioneering stealth aircraft have been kept in special climate controlled storage hangers in the event they were ever needed again. Now, Congress is considering removing those mothballed aircraft and having them scrapped and gutted for hard-to-find parts.

April 28/16: The forth and final test aircraft of Boeing’s KC-46A tanker program has made its maiden flight. While not kitted out for aerial refueling, the 767-2C aircraft will be used to conduct environmental control system testing for the program. The arrival of the latest tanker comes as Boeing scrambles to complete a “milestone C” review by the Office of the Secretary of Defense (OSD). A favorable review will unleash additional funds needed for the program, including a seven tanker production order, which the manufacturer had already begun producing out of its own pocket.

April 13/16: Despite development setbacks and a recent Milestone C demonstration hiccup, Boeing believes that it can deliver 18 operational KC-46 Pegasus tankers within six months instead of the original 14. The plan has been labelled “optimistic” in a new report by the US Government Accountability Office (GAO). While the GAO notes that most of the issues have been amended successfully, the recent problems seen in the aircraft’s centerline drogue system and wing aerial refueling pods may make this optimistic projection nothing but wishful thinking.

April 5/16: The otherwise fast pace of the KC-46A’s aerial refueling demonstration phase has started to run into difficulty. Testing on refueling of Boeing’s C-17 heavy cargo lifter has resulted in higher than expected boom axial loads, caused by two large aircraft flying in line. This bow-wave effect has subsequently caused the system to indicate that the loads were too high to begin passing fuel. Subsequent delays caused by the issues have resulted in scheduled trials of the A-10 attack aircraft being pushed back, and any further issues may impact a low-production rate decision due to be made at the end of May.

March 24/16: The Defense Contract Management Agency has expressed its “low confidence” in Boeing’s ability to deliver the KC-46A on time. Delivery of the tanker to the USAF is expected by August 2017 and is currently in the process of undergoing its Milestone C Demonstrations. Despite this, the agency now believes Boeing can only deliver the 18 KC-46As by March 2018, and there is a possibility that the new date might not be achievable either.

March 7/16: Boeing’s second KC-46A aerial refueling tanker has made its first flight. The aircraft will be used to test mission system avionics and exterior lighting before moving onto sharing the air refueling effort with the first KC-46. With a second fully configured tanker, Boeing can move through “receiver certification” for 18 aircraft types a lot more quickly. At present, the KC-46 has already demonstrated functionality with the Lockheed Martin F-16, Boeing F/A-18 and refueling from a Boeing KC-10.

February 26/16: Despite a successful start to the KC-46 Milestone C demonstrations, Boeing is still under pressure to keep to its tight window to have 46 of the tankers operational by August 2017. The original schedule is at present eight months behind after a number of setbacks, and leaves little room for error until the delivery deadline. While funding of the program and technical difficulties are not a contributing factor, it’s feared that the Air Mobility Command (AMC) won’t have sufficient time for the 767-2C-based tankers to declare initial operational capability on schedule.

February 24/16: The KC-46 is halfway through its six aerial contact tests as part of the program‘s “Milestone C” demonstrations. The tanker has now successfully demonstrated all three of its major fuel systems after being successfully topped up by another KC-10 aircraft. The February 16 test follows the refueling of a F-16 and F/A-18 over the last number of weeks, and keeps the program right on track for a low-rate initial production decision in May. The three remaining tests will involve probe-and-drogue testing with a US Navy AV-8B Harrier II jump jet, followed by boom refueling of a Fairchild Republic A-10 and Boeing C-17.

February 16/16: Testing of the refueling capabilities of the KC-46 tanker has hit another target with the successful refueling of an F/A-18 fighter. This follows its first ever refueling flight on January 24, where it successfully refueled an F-16. While the first test utilized the tanker’s refueling “boom,” a rigid, telescoping tube that an operator on the aircraft extends and inserts into a receptacle on the receiving aircraft for fuel transfer, the F/A-18 test was the program’s first usage of the KC-46’s hose and drogue system. Located on both the plane’s wing and centerline, the hose and drogue system enables the KC-46 to refuel smaller aircraft such as the F/A-18 with up to 400 gallons of fuel per minute. All tests are part of the program’s Milestone C demonstration before a low-rate initial production decision is made later this year.

February 11/16: An Israeli news source has reported that the US government has cleared the sale for two of Boeing’s newest KC-46A Pegasus aerial refueling tankers to Israel via the security assistance package. The Pentagon had originally put a pause on selling new aircraft to Israel, initially offering them older models. However, Israel has been insisting on the latest multi-mission tanker with the deal only approved upon the completion of the nuclear deal with Iran. The tanker sale could have become a point of contention for Tehran as its specs allow for a range of 7,350 miles with in-flight refueling. With an average price tag of $188 million each, the addition of Israeli system modifications will see each aircraft cost a quarter of a billion dollars.

January 26/16: The USAF and Boeing have reached an important milestone in the development of the KC-46 tanker after it successfully carried out a mid-air refueling of an F-16 jet. Prior to the refueling, both had checked a number of test points during the flight, with a successful demonstration necessary before Boeing can enter the plane into low rate production. The USAF has ordered 176 of the tankers to replace their KC-135 Stratotankers with the first eighteen of the tankers needed to be operational and ready to go by August 2017.

October 26/15: In a not unexpected decision, the Japanese Defence Ministry has opted to buy three KC-46A Pegasus tankers, marking the first international sale of the aircraft, which is still in development. The three new aircraft will bolster the JASDF’s fleet of four KC-767s, with each of the new aircraft thought to value $173 million. The KC-46As are slated for fielding in 2020, with the Boeing bid fending off competition from Airbus’ A330 MRTT. Elsewhere in the region, South Korea selected the Airbus design in July, signing a contract for four A330-MRTTs.

October 23/15: The KC-46A Pegasus tanker EMD-1 development aircraft has arrived at Edwards AFB for two weeks of work, including Ground Effects and Fuel Onload Fatigue tests. The latter involves learning more about how the aircraft operates when taking on fuel from another tanker, such as a KC-135 or KC-10, while Ground Effects testing collects data to incorporate into the aircraft’s simulator. The other development aircraft (EMD-2) deployed its refuelling boom for the first time in October, with EMD-1’s maiden flight in September.

October 12/15: The KC-46A Pegasus tanker has deployed its refuelling systems for the first time, including its boom, hose and drogue systems. The tanker performed its first flight in September, following a delay in August. Boeing is working towards an initial operating capability – which will see 18 KC-46A and support available for operations – by August 2017.

October 9/15: Two Air Force pilots have been cleared to fly the KC-46A Pegasus tanker, which performed its first test flight in late September. The pilots will be used for military certification of the aircraft, which is also required to pass FAA regulations. The Air Force is eventually scheduled to receive 179 KC-46A tankers under a contract awarded to Boeing in February 2011; the fixed-cost nature of the contract means that Boeing has been forced twice to absorb development costs, with the Air Force’s costs capped at $4.9 billion.

FY 2015

 

September 28/15: A fully-configured KC-46A tanker completed its first flight on Friday, a month later than scheduled owing to the chemical mix-up in early August. The program is a year behind schedule, the first flight is a rare positive sign for a program hit by cost spikes and schedule delays, with Boeing scheduled to deliver 18 aircraft in August 2017.

September 18/15: With Airbus walking away from the competition earlier this month, the Japanese Defense Ministry has reportedly selected the Boeing KC-46A to supply the country’s next generation refuelling tanker. Price negotiations are now scheduled, with the number of tankers the Defense Ministry plans to procure not yet determined. Boeing lost out in South Korea to the Airbus A330 MRTT in July.

September 17/15: The first KC-46A tanker is expected to fly on 25 September, following a year-long delay. The trouble-hit tanker has become a headache for Boeing, which has been absorbing increasing development costs through a firm-fixed contract signed in February 2011 which capped Air Force costs at $4.9 billion. The most recent setback resulted from an accident involving the insertion of chemicals into the aircraft’s refuelling system in early August, pushing the tanker’s schedule back by a month.

August 19/15: The mistake earlier this month involving the accidental insertion of chemicals into the fuel system of the KC-46A tanker has officially delayed the aircraft’s first flight by a month. The tanker will now see its first flight in late-September or early October, with the program’s original timetable calling for this flight to have taken place last year, with this pushed back to April and then again to late August, before this latest setback.

July 1/15: South Korea has selected Airbus’ bid to supply the country’s Air Force with four refueling tankers, beating competitors Israel Aerospace Industries and Boeing for the $1.07 billion program. The winning bid – the A330 MRTT – dashed Boeing’s hopes of securing its first export order for the KC-46A, which saw a strong dollar raise its bid price compared with a weakened euro for the European bid. The four tankers are scheduled for delivery in 2019.

June 10/15: NAVAIR has been slamming missiles into the side of its KC-46 tankers as part of Naval Air Warfare Center Weapons Division survivability testing at the Weapons Survivability Laboratory. The tests used – among other sensors – ten high-speed cameras to capture the impact of the test missiles, themselves specifically designed to inflict maximum possible damage to the aircraft. The Air Force intends to buy 179 of the tankers to replace approximately a third of the current tanker fleet, which consists principally of KC-135 Stratotankers.

April 24/15: Tinker Air Force Base (Oklahoma) has been named as one of four potential locations to base the Air Force’s fleet of new KC-46A refueling tankers, alongside Seymour-Johnson Air Force Base (North Carolina), Westover Air Reserve Base (Massachusetts) and Grissom Air Reserve Base (Indiana).

Jan 26/15: Flight test. Boeing conducted a flight test from Payne Field in Everett, Washington. The four-hour flight was uneventful, but well-documented.

Dec 10/14: spares. Boeing is awarded a not to exceed $84.5M undefinitized contract action modification (P00054) to previously awarded contract FA8625-11-C-6600 for 4,880 production support equipment items and 6 production spare parts. Work will be performed at Seattle, WA, and is expected to be completed by June 30, 2016. $9.5M in FY14 aircraft procurement funds and $32.2M in FY15 aircraft procurement funds are being obligated at the time of award.

Dec 03/14: wiring. Boeing Dennis Muilenburg told investors during a conference organized by Credit Suisse that wiring problems that had led to delays and charges (q.v. Sept 17/14) were now “resolved and closed out.”

Dec 01/14: Training. The USAF intends to finalize its Maintenance Training System (MTS) RFP in January 2015. The draft, released back in September, is found under solicitation IDN-KC-46-MTS.

Nov 24/14: Personnel. The Air Force Personnel center announces that the aircrew of 41 officers and enlisted members from the active force, Reserve and National Guard have been selected to staff initial operational test and evaluation (IOT&E).

Nov 19/14: Schedule. The USAF publicly admits what KC-46A program watchers already know: Boeing is essentially out of schedule margin to deliver the 767-based KC-46As on time by 2017. The USAF is still describing the contract as “achievable,” but so many things have to go right that this isn’t a smart bet for outside observers. The USAF won’t really say anything else until disaster is certain, though, because the admission will make the service look bad (q.v. March 4/11). Sources: Reuters, “US Air Force sees challenges on Boeing KC-46 tanker program”.

Oct 16/14: Delays. Boeing finally admits that the KC-46A’s program schedule will have to be changed. They don’t know how many milestones will need adjustment, but they’re still holding to the idea that they’ll have 18 KC-46As delivered by August 2017.

Can they avoid proving Airbus’ March 4/11 prediction that Boeing would deliver late? It’s hard to see how Boeing’s on-time promise adds up now, given significant GAO and DOT&E concerns that the testing program as proposed is too compressed and can’t be executed (q.v. April 11/14, Sept 17/13). Boeing gets to try convincing Pentagon acquisition officials with an official submission early in 2015, and the USAF will then conduct its own “schedule risk assessment” to examine Boeing’s assumptions.

Most ways of speeding up programs involve spending more money, though that tends to have diminishing returns past a certain point. The program’s official cash reserve is expected to run dry in March 2015, but the USAF’s costs are capped, so it’s likely that Boeing will wind up spending more private funds on KC-46A development. Sources: Bloomberg, “Boeing Seeks Revised Schedule for U.S. Aerial Tanker”.

FY 2014

Competition in South Korea? Initial basing decisions; Boeing takes extra costs charge, announces delays.

[youtube:v=hwwHCN_Vayw]

Workers saluted

Sept 17/14: Flight delay. First flight for the KC-46A is in question due to the same wiring bundle technical issues that forced Boeing to take an additional $272 million Q2/14 charge on the program (q.v. July 23/14). USAF spokesman Ed Gulick:

“We are disappointed with Boeing’s current KC-46 production challenges and their inability to meet internal production milestones, but we do not see anything of great concern and are confident they will overcome the issues,” said Gulick in a statement to Puget Sound Business Journal. “The KC-46 program’s technical and cost performance are on-track; Boeing has met every contractual requirement to date.”

The baseline 767 has about 70 miles of wiring in the design, and the need for redundancy in certain systems pushes the 767-2C to 120 miles, including shielding requirements and mandatory separation distances for safety reasons. The redesign will address these issues, but it sideswipes plans for concurrent installation in the 4 test aircraft currently under construction. Given the program’s known issue with compressed test schedules (q.v. April 11/14), they had better be ready by April 2015. Sources: Aviation Week, “First Flight for KC-46 Tanker Platform Slips Further” | Puget Sound Business Journal, “Air Force ‘disappointed’ in Boeing tanker delays; issues cost Boeing millions”.

Sept 15/14: Training. The USAF issues a Draft Request for Proposal (DRFP) for the KC-46 Maintenance Training System (MTS) Program. It consists of various specific component trainers, e-learning materials, and Training System Support Center build-outs. Sources: FBO.gov, “KC-46 Maintenance Training System, Solicitation Number: IDN-KC-46-MTS”.

Aug 5/14: Basing. The USAF announces that the KC-46A’s MOB2 Air National Guard base will be Pease ANGB, NH, which beat Forbes AGS, KS; Joint-Base McGuire-Dix-Lakehurst, NJ; Pittsburgh International Airport AGS, PA; and Rickenbacker AGS, OH.

Pease has apparently been the preferred alternative since May 2013, owing to its location in a region of high air refueling receiver demand and successful ANG-USAF partnership. This announcement follows the required environmental reviews. Sources: Pentagon NR-409-14, “Pease Air National Guard Base selected to receive KC-46A Pegasus aircraft”.

Basing: MOB2 ANG picked

July 23/14: Cost. During a Q2 analyst conference call, Boeing CEO Jim McNerney says that they’re absorbing a $272 million unexpected charge related to problems with KC-767 wiring harnesses:

“We bid the EMD (engineering manufacturing and development) contract for the tanker aggressively, with zero margin, with planned profitability in the production phase. Despite our disappointment in encountering these challenges, the issues are well understood, and no new technology is needed to solve them…. We have a wet fuel lab, a lighting lab, those have all been put in place to de-risk the program. We have a wet lab where we are running fuel through pumps and valves to validate that on the ground.”

Sources: Boeing, “Boeing Reports Second-Quarter Results and Raises 2014 EPS Guidance” | Puget Sound Business Journal, “Boeing: We can fix Air Force tanker problems without new technology”.

July 14/14: Cost. The KC-46A development phase could end up costing Boeing more than expected. That may concern Boeing executives, but the USAF won’t pay any more and doesn’t care:

“Defense Undersecretary Frank Kendall told reporters late on Sunday that Boeing was performing “satisfactorily” on the KC-46 tanker program, but several events – including water damage caused by a sprinkler malfunction at the company’s Everett, Washington plant – meant costs were higher than expected.”

Boeing says that they’ll be able to cut costs with their testing approach. We’ll see. Sources: Reuters, “AIRSHOW-Boeing may face higher than expected costs on KC-46 tanker”.

June 30/14: South Korea. Boeing confirms that they’ve formally offered South Korea the KC-46A tanker being developed for the USAF, rather than the KC-767 model that’s already in service with Japan and Italy. They tout the KC-46A’s quick-conversion main deck cargo floor, but in the face of North Korea’s WMD arsenal, and ability to target ROKAF bases with missiles, they make a point of mentioning that:

“Unique among tankers, the KC-46 can operate in chemical, biological and nuclear conditions, features cockpit armor for protection from small arms fire, and can also operate from a large variety of smaller airfields and forward-deployed austere bases.”

Sources: Boeing, “Boeing Offers Next-Generation KC-46 Tanker in Republic of Korea Competition”.

June 4/14: Infrastructure. The Ross Group Construction Corp. in Tulsa, OK wins a $17.5 million firm-fixed-price contract with options, to built the KC-46A Fuselage Trainer Flight Training Center and the Fuselage Trainer at Altus AF, OK. Option 4 for sidewalks and landscaping, and Option 5 for additional concrete parking stalls, are exercised at time of contract award. Altus AFB was recently chosen as the KC-46A’s main training base (q.v. April 23/14), and already operates in that capacity for the KC-135 fleet.

The estimated completion date is Oct 5/15. Bids were solicited via the Internet, with 7 received by the US Army Corps of Engineers in Tulsa, OK (W912BV-14-C-0015).

May 29/14: Infrastructure. MEB General Contractors in Chesapeake, VA wins an $8.4 million firm-fixed-price contract for construction services to alter the KC-46A apron fuels distribution system and supporting facilities at McConnell AFB, KC, and to relocate fuel vents/valves at the 3-bay hangar and 2-bay hangars.

All funds are committed immediately, using FY 2014 military construction budgets. Work will take place at McConnell AFB (KC-46A MOB1), with an estimated completion date of Dec 3/15. Bids were solicited via the Internet, with 2 received. The US Army Corps of Engineers in Kansas City, MO manages the contract (W912DQ-14-C-4010).

[youtube:v=EWqa2qEIZWc]

Flight Simulator

April 23/14: Basing. The Pentagon announces that McConnell AFB, KS will be is the KC-46A’s active duty-led MOB1 Pegasus main operating base. McConnell won because swapping in 36 KC-46As for 44 KC-135s involved the lowest military construction costs, and the base is located in a high-demand area. McConnell was also seen as “an ideal central location for the new KC-46A Regional Maintenance Training Center.” It beat Fairchild AFB, WA (2 KC-135 Sqns), Grand Forks AFB, ND (1 KC-135 Sqn), and Altus AFB, OK, all of whom will continue to operate KC-135s.

By default, Altus AFB, OK will continue in its FTU tanker training role, which it already performs for the KC-135. Advantages to keeping it in a training role include co-location with both tanker and heavy receiver aircraft for training purposes, and “considerably fewer” new construction requirements vs. McConnell. Altus will begin receiving KC-46A planes in 2016.

The Air National Guard MOB2 base (q.v. Jan 9/13) remains undecided, and will be picked in summer 2014. It will be 1 of Forbes Air Guard Station, KS (whose chances have probably dropped); Joint-Base McGuire-Dix-Lakehurst, NJ; Pease Air Guard Station, NH; Pittsburgh International Airport Air Guard Station, PA; and Rickenbacker Air Guard Station, OH. The winner will begin receiving planes in 2018. Sources: Pentagon, “Air Force Announces Bases to House New Tanker Refueling Aircraft”.

Basing: MOB1 & FTU picked

April 17/14: SAR. The Pentagon finally releases its Dec 31/13 Selected Acquisitions Report [PDF]. The KC-46A has seen the Pentagon’s program costs go down:

“Program costs decreased $2,181.5 million (-4.2%) from $51,642.1 million to $49,460.6 million, due primarily to lower construction estimates based on site surveys of initial bases (-$715.4 million), funding reductions in FY 2015-2018 given stable program execution and no engineering change proposals to date (-$655.6 million), and the removal of construction planning and design funding from FY 2014-2024 budgeted elsewhere (-$268.8 million). Additional program cost decreases included the application of revised escalation indices (-$222.7 million), accelerating the procurement buy profile (-$157.7 million), and sequestration reductions (-$142.9 million).”

Cost decrease

April 11/14: GAO Report. The US GAO tables “KC-46 Tanker Aircraft: Program Generally on Track, but Upcoming Schedule Remains Challenging“. Flight testing is scheduled to begin in June 2014 for the 767-2C, and in January 2015 for the KC-46, but it will be a bit of a squeeze making that:

“The KC-46 program has made good progress to date—acquisition costs have remained relatively stable, high-level schedule and performance goals have been met, the critical design review was successfully completed, and the contractor is building development aircraft. The next 12 months will be challenging as the program must accomplish a significant amount of work and the margin for error is small. For example, the program is scheduled to complete software integration and the first test flights of the 767-2C and KC-46. The remaining software development and integration work is mostly focused on military software and systems and is expected to be more difficult relative to the prior work completed [which is generally on schedule]. The program’s test activities continue to be a concern due to its aggressive test schedule. Detailed test plans must be completed and the program must maintain an unusually high test pace to meet this schedule. Perhaps more importantly, agencies will have to coordinate to concurrently complete multiple air worthiness certifications. While efficient, this approach presents significant risk to the program. The program office must also finalize agreements now in progress to ensure that receiver aircraft are available when and where they are needed to support flight tests.”

The GAO and the Pentagon’s DOT&E group continue to believe that Initial Operation Test & Evaluation should be pushed back 6-12 months, in order to train aircrew and maintenance personnel and verify maintenance procedures. The USAF isn’t convinced yet, and knows that this move would delay the entire project for a similar period. Furthermore, the testing schedule itself is so concurrent that any problems found during test are almost certain to create delays to the program as a whole. One technical area that could still bite them involves “lingering instability in…. the centerline drogue system and wing aerial refueling pod,” but Boeing hopes to fix that before flight testing begins.

Finally, as of December 2013, the original $354 million program reserve budget has just $75 million (21.1%) left, leaving the program at risk of running out before testing begins. As long as the USAF doesn’t change the design, however, that’s Boeing’s problem.

March 31/14: GAO Report. The US GAO tables its “Assessments of Selected Weapon Programs“. Which is actually a review for 2013, plus time to compile and publish.

The KC-46 Tanker program comes in for praise in a couple of areas. One has to do with the “should-cost” method for the final product, which will reportedly save $6.8 billion over the total program, with $6.4 billion listed as already realized. The other area that drew praise was the program’s use of all 4 best practices for development programs: (1) identifying key product characteristics; (2) identifying critical manufacturing processes; (3) conducting producibility assessments to identify manufacturing risks; and (4) completing failure modes and effects analysis to identify potential failures and early design fixes. Boeing should be motivated to do all that, because their contract makes them fully responsible for any fixes required in early production aircraft.

Costs remain almost identical to initial estimates, so far. The bad news is that test boom production has been delayed by almost a year due to design changes and late parts, but Boeing hopes to have it ready in time for initial KC-46A flight testing in January 2015.

March 4-11/14: FY15 Budget. The US military slowly files its budget documents, detailing planned spending from FY 2014 – 2019. The KC-46A program’s revised totals are reflected in the article’s charts, and the USAF has worked hard to protect the program. What’s interesting is the program’s schedule. It hasn’t been changed officially, but Air Mobility Command isn’t giving an official Initial Operational Capability date.

Previous years had listed budgets for spares, but those have effectively been revised. A contractor service agreement for the initial planes will see also spares bought as part of the procurement budgets, until the USAF takes over all maintenance itself.

Feb 20/14: KC-46 Pegasus. USAF Gen. Mark Welsh announces that the KC-46A will be the “Pegasus”. Air Force Secretary Deborah Lee James had approved the recommendation from Air Mobility Command boss Gen. Paul Selva earlier in the week. Sources: AFA Air Force Mag, “Introducing the KC-46A Pegasus” | Everett Herald, “Air Force dubs KC-46A tanker ‘Pegasus'”.

KC-46 Pegasus

Jan 16/14: Industrial. Boeing has begun assembling the 4th and final KC-46A test aircraft, and says that the program remains on track to deliver the initial 18 tankers to the Air Force by 2017. According to the current schedule, the 1st flight of a KC-46 test aircraft will take place at mid-2014 without its aerial refueling systems, followed by the first flight of a full KC-46A tanker in early 2015.

The first delivery of a production aircraft to the Air Force is planned for early 2016, but of course that depends on things going well during testing. Official reports to date have been skeptical, so no matter how things turn out, someone is about to be proved wrong. Sources: Boeing, “Boeing Starts Assembly of Final KC-46A Test Aircraft”.

Nov 5/13: Infrastructure. URS Group Inc. in Mobile, AL receives a $13 million firm-fixed-price, indefinite-delivery contract for architect-engineering services to support USAF KC-46 beddown in the continental United States. The 767 is closer in size to the KC-135, which means that it needs fewer infrastructure changes than the A330/ KC-45.

There will still be facilities and features to build (q.v. FBO.gov, Oct 2/13). Estimated completion date is Nov 14/18, with work location and funding determined with each order. Bids were solicited via the internet, with 57 received by the Army Corps of Engineers in Mobile, AL (W91278-14-D-003).

Oct 22/13: Industrial. Boeing announces that assembly of the 3rd aircraft and 2nd boom are underway. They sound confident that manufacturing of the initial batch of 4 aircraft remains on track to be completed by Q3 2014.

This would be good news for their USAF client, and would also help the company make its case in South Korea (q.v. Aug 7/13), where parliament is about to review whether to proceed with a competition for 4 tankers to be delivered in 2017-19. Sources: Boeing, Oct 22/13 release.

Oct 2013: Basing. Public hearings scheduled at the end of the month in Kansas and Oklahoma are postponed on October 11 because of furloughs at the Environmental Protection Agency (EPA) during the government shutdown. As of Oct 23, a new date for the hearings had not yet been released. Meanwhile the Air Force Civil Engineer Center (AFCEC) and the US Army Corps of Engineers are preparing infrastructure work: AFCEC | Industry Day | Sources Sought.

FY 2013

Design finalized after CDR; State of the program reports; Sequester threat; Basing competition; Training aids picked.

KC-46A & B-2A concept

KC-46A and B-2
(click to view full)

Sept 17/13: Testing. KC-46A program executive Gen. John Thompson offers a bit of clarity regarding testing plans. The first 4 planes will be split between the commercial 767-2C baseline, which is set to fly in January 2014, and 2 fully converted KC-46A tankers, which won’t fly until June 2015. Civil certification is an important precursor to the military supplemental certification (q.v. May 31/13), and the 767-2Cs will eventually become KC-46As to support initial operational test and evaluation.

Thompson sounds very confident about the intensive testing schedule, but then, he needs to. Past GAO and DOT&E reports have flagged it as a program risk (q.v. Jan 17/13, Feb 27/13), and have even called the test plan “not executable” (Jan 17/12). Sources: NDIA Magazine, “Newly Designed KC-46 Aerial Refueling Tanker to Undergo Strenuous Testing”.

Sept 4/13: Boeing announces that the USAF has validated the final design elements of the KC-46A, concluded that it meets requirements, and frozen the plane’s configuration. That clears the way for production and testing.

Design is set.

Aug 7/13: South Korea. Yonhap reports that South Korea may acquire 4 aerial refueling tankers by 2019. It seems to be at the discussion level rather than a firm decision. If it proceeds, Boeing’s KC-46A and Airbus Military’s A330 MRTT are seen as the logical contenders, and the 2019 date makes the KC-767 a viable possibility.

The A330’s challenge is that, unlike Australia, South Korea’s zone of action doesn’t really need the A330’s range and size. That will make the extra expense problematic. It’s also worth noting that South Korea already has significant defense relationships with Israel’s IAI. That could create an opening for IAI’s much cheaper K-767 MMTT option, which is also on offer to Singapore. Sources: Yonhap News, “Air Force to acquire 4 aerial refueling tankers by 2019”.

July 10/13: CDR. KC-46A Weapon System Critical Design Review takes place, and is successful. Source: Boeing, Sept 4/13 release.

CDR

July 3/13: Sub-contractors. Fleet Canada Inc. in Fort Erie, ON receives its 1st order from Boeing, for sub-assemblies of the KC-46A Camera and Boom Fairings. The contract is issued as part of Boeing’s industrial offset requirements for various Canadian defense buys, including the C-17A airlifter and CH-47F Chinook helicopter. Fleet Canada.

June 26/13: production. Boeing announces that production of the first aircraft has begun. The USAF’s Critical Design Review (CDR) will start in July 2013, as announced last year. Beyond that, the company is forecasting the following milestones:

* First aircraft assembly: Nov. 2013-January 2014
* First flight: 2015
* First delivery: 2016
* Delivery of the first 18 aircraft by August 2017

June 16/13: Exports. Boeing told reporters that Boeing is engaged in talks with several export prospects in Asia and the Middle East, for a total of 20 potential units. The company’s defense and civilian arms are working together to be able to make the aircraft available for sales abroad by 2017. Bloomberg | DoD Buzz.

May 31/13: Certification process. Boeing will seek FAA certification in 2 phases: first there is one for the commercial 767-2C aircraft, then a supplemental one for the military modifications to the commercial aircraft.

In March 2012, the GAOlisted the fact that Boeing planned to pursue some parts of these 2 certifications in parallel as a risk factor. John Howitt, the program deputy manager, told AIN that this is addressed with joint technical planning and work, even though the 2 certifications are separate from an administrative perspective. Sources: AIN.

May 1/13: Training. Berkshire Hathaway company FlightSafety Services Corp. in Centennial, CO wins a $78.4 million fixed-price-incentive-firm and firm-fixed-price contract to design, develop, and build the KC-46 aircrew training system, including delivery of courseware and simulator-based training systems. FlightSafety will design and manufacture the KC-46, Boom Operator, and Part Task Trainers at its 375,000 square foot simulation facility in Oklahoma; the first device is scheduled for delivery in February 2016.

FlightSafety is no newcomer to this role, with operations at 15 U.S. Military bases that include Flight School XXI; Training systems for the KC-10 Extender, C-5 Galaxy, C-17 Globemaster, AFSOC’s HC-130P Combat King, and the V-22 Osprey tiltrotors; and Contractor Logistics Support for the T-6 JPATS and T- 37/38 trainers. The KC-46A contract pays $1 million initially, with the rest to be paid over time, including additional production and operations options that could raise its value beyond $78.4 million. Warren Buffett will be glad to hear that.

Work will be performed at Broken Arrow, OK and St. Louis, MO and is expected to be complete by 2026 if all options are exercised. This award is the result of a competitive acquisition, with 5 offers received by USAF Life Cycle Management Center/WNSK’s Simulators Division (FA8621-13-C-6247). See also USAF | FlightSafety International.

April 17/13: Sub-contractors. ITT Exelis announces a contract from Raytheon Company (NYSE: RTN) to supply its anti-jam N79 CRPA (Controlled Reception Pattern Antenna) GPS antennas, for use with Raytheon Navshield and Advanced Digital Antenna Production equipment on the KC-46A. Work will be performed in Bohemia, NY.

April 13/13: Restructure at peril. USAF AMC commander Gen. Paul J. Selva reiterates the KC-46A’s #1 priority status for the Air Force, and warns about the effects of restructuring this contract:

“…because we have a firm fixed-price contract for the development of that airplane, if we allow ourselves to get into the position where we don’t have the funds to pay for the initial development of the airplane, that contract gets reopened…. We’ll pay more…”

Probably. Boeing bid hundreds of millions of dollars below development cost to win KC-X, but 2 years into the contract, the US military’s ability to switch to Airbus is more limited. They’d have to delay their #1 priority program, while creating a lot of opposition in Congress. There are creative ways to charge more in total, and Boeing would be well placed to negotiate a few in any restructuring.

April 10/13: FY 2014 Budget. The President releases a proposed budget at last, the latest in modern memory. The Senate and House were already working on budgets in his absence, but the Pentagon’s submission is actually important to proceedings going forward. See ongoing DID coverage. For KC-X, it’s pretty much steady as she goes, hewing more or less to previous plans.

Total reductions from FY 2014-2017 are around $182 million compared to FY 2013 plans, but a fixed-price contract is going to have to reach the agreed total regardless. Current budgets show just $3.173 billion allocated for RDT&E from FY 2011 – 2018, but the USAF is near-certain to owe $4.7 billion for the EMD phase.

April 7-10/13: Basing. As the USAF prepares to make decisions about where to base its KC-46s, communities are competing. The catch is that there are really 2 initial competitions, and they’re mutually exclusive (q.v. Jan 9/13 entry). Grand Forks Herald | Lawton Constitution | Wichita Eagle.

Feb 27/13: GAO Report. The GAO’s annual in-depth look at the KC-46 program is out. The good news is that after 28% ($1.4 billion) in development work, the program costs and schedule haven’t changed much. The CDR is still scheduled for July 2013, albeit with some risks. The USAF and Boeing are evaluated as managing the project well, and have added the ability to track progress toward key aircraft performance goals.

Concerns fall into 3 areas: financial reserves, weight, and software. The GAO is one of several agencies that think flight testing and certification will need to take about 6 months longer, and the boom refueling system is changing a bit, but those are secondary risks right now.

The development contract set aside about 7% ($354 million) in reserves, and 2 years into a 7-year development program, 79.6% of those reserves have been spent, leaving less than $72 million to cover an expected $3.5 billion in work. Some of the issues driving this spending aren’t resolved yet. As we explained above, the government’s costs won’t change if this problem isn’t solved, but GAO is worried about technical problems growing and creating schedule issues.

Projected weight is now expected to exceed the KC-46’s target weight, and each pound above target reduces fuel payload by 1 pound. Extra weight could also affect operating requirements for takeoff, mission radius, and landing. The program has a mitigation strategy in place, and further weight reduction initiatives can create tradeoffs in areas like durability and cost.

Software is a good news/bad news story. They’ve cut total software development by 40%, but code reuse will be less than planned (52% vs. 76%), which means new and modified software has doubled to 48% from 24%. That means more work overall and more testing, though program officials are claiming that schedules won’t be affected.

Feb 22/13: KC-135Rs retiring. After more than 50 years of service and 22,500 flying hours, the 1st operational re-engined KC-135R Stratotanker retires from service, and heads to AMARG’s “boneyard” at Davis-Monthan AFB, AZ. KC-135R #61-0312 first flew as a KC-135A on Aug 14/62, and was re-engined into a KC-135R on June 27/85.

This plane’s retirement is budget-driven, as 1 of the 16 scheduled KC-135 retirements in FY 2013. On the other hand, the KC-135 Program Office at Tinker AFB, OK used the Fleet Health Analysis Tool to pick the aircraft. Joey Dauzat, 97th Maintenance Directorate KC-135R sortie generation flight chief, discussed KC-135 usage patterns, which will become much more relevant if something happens to the KC-X program:

“[KC-135Rs] assigned to Altus Air Force Base fly approximately 1,820 sorties per fiscal year, which averages out to 91 sorties per aircraft…. Flight hours are approximately 7,030 hours per fiscal year, which averages out to 351 flight hours per aircraft. All sorties are required to have [refueling booms] on them, so every sortie flown is a boomer training sortie.”

Feb 2/13: A USAF presentation to Congress says that if sequestration takes effect, the KC-46A program may need to be restructured, along with the F-35 fighter and MQ-9 Reaper Block 5. Flight International.

Feb 2/13: High Usage. The USAF is planning to use KC-46As more intensively than their KC-135 counterparts. That makes sense on several levels: (1) As a way to save money by flying the more expensive-to-operate KC-135s less; (2) As a way to build in surge capability for the KC-46As if the KC-135 fleet has a problem; and (3) As a pre-conscious recognition that KC-X is probably the USAF’s entire future aerial tanker fleet.

The KC-135’s average of 2.5 aircrews per plane will rise to 3.5 aircrews for the KC-46A, adding about 60 full aircrews to the force, and costing about 11.2% more for KC-46A lifetime operations and maintenance because they will be flying more often. Total operations and support costs are now predicted to be approximately $103 billion, but the $10 billion or so rise would be offset by any savings from fewer flights of the more expensive KC-135Rs. USAF.

Higher usage planned

Jan 17/13: DOT&E testing. The Pentagon releases the FY 2012 Annual Report from its Office of the Director, Operational Test & Evaluation (DOT&E). The USAF has bought 2 767-200s for live fire testing, and is planning the survivability assessment, including LAIRCM tests. They do have one major concern:

“The ALR-69A RWR [radar warning receiver] was selected as Contractor Furnished Equipment by Boeing; however, integration and performance on the KC-46A are high risk. DOT&E recently completed an assessment of the ALR-69A RWR on the C-130H1 and assessed it as not effective, but suitable, in a separate classified report dated October 22, 2012. Not only do these effectiveness problems require correction, but the system is required to improve its geo-location capabilities as compared to the demonstrated C-130J capability.”

DOT&E also has some technical issues with the overall testing plan. The 750 hours of operational testing over 5.5 months can establish effectiveness, but getting 76% confidence of suitability (maintainability) would need 1,250 hours. This was also pointed out in last year’s report, and it will need to be worked out one way or another.

Jan 9/13: Basing. The USAF announces KC-46A initial basing candidates, while stressing that losing bases will continue to operate KC-135s. The USAF doesn’t mention this, but the FTU training and MOB1 operating base awards are mutually exclusive: you can win one, but not both. There’s no overlap at all with the ANG’s MOB2 locations, so those have to be separate. Candidates include:

Formal Training Unit: Altus AFB, OK vs. McConnell AFB, KS. Altus already performs the FTU role for the KC-135. Winner begins receiving planes in 2016.

Active Duty Main Operating Base (MOB 1): One of Altus AFB, OK (KC-135 FTU); Fairchild AFB, WA (2 KC-135 squadrons resident); Grand Forks AFB, ND (1 KC-135 squadron resident), and McConnell AFB, KS (4 KC-135 squadrons resident). Winner begins receiving planes in 2016.

Air National Guard MOB 2: One of Forbes Air Guard Station, KS; Joint-Base McGuire-Dix-Lakehurst, NJ, Pease Air Guard Station, NH; Pittsburgh International Airport Air Guard Station, PA; and Rickenbacker Air Guard Station, OH. Winner begins receiving planes in 2018.

Oct 16/12: Industrial. Boeing opens the KC-46 Boom Assembly Center on schedule at Boeing Field in Seattle, WA. Boom assembly marks the program’s shift to production from design activities, and the 1st fly-by-wire boom is scheduled to enter testing during Q3 2013 at Boeing Field’s System Integration Labs. Boeing.

FY 2012

Basing plans; Preliminary Design Review; Industrial decisions.

KC-46A

‘Paper airplane’ risks?
(click to view full)

Sept 12/12: Industrial. Boeing opens System Integration Lab 0 at Boeing Field, 3 weeks ahead of schedule. SIL 0 will be used to test commercial avionics and software for integration into the KC-46A Tanker. Another 3 SILs will open at Boeing Field and a 5th will open in Everett, WA by the end of 2013.

Boeing Field is also slated to house the program’s Boom Assembly Center, and the Finishing Center. The Finishing Center is scheduled to open in late 2013, and will be used to install military hardware and software onto the commercial 767-2C airframe. Boeing.

July 27/12: Sub-contractors. Eaton Corp. announces a supplementary contract from Boeing, which adds the aerial refueling pump system, the aerial refueling boom nozzle, and various airframe and aerial refueling system valves and fuel/ actuation components. See also June 18/11 entry.

June 13/12: Industrial. Boeing VP and KC-46 program manager Maureen Dougherty talks about moves Boeing is making since the announcement that it was closing the Wichita, KS facility. That closure creates added risk, but Boeing is sticking to its estimates and trying to offset it.

Three systems integration laboratories (SILs) will be located at Boeing Field in the southern part of Seattle, WA, but they won’t be operational until fall 2012. Flight testing, a full lab replica of the entire KC-46 fuel architecture, and the finishing center’s 2 workstations will also be there. They’ve also begun wind tunnel testing with Cobham regarding the shape of the plane’s refueling pods, a move that underlines the developmental nature of key items. Aviation Week.

May 14/12: Initial bases. The USAF decides that the KC-46A’s formal training unit (FTU) and first main operating base (MOB 1) will be led by active duty units, while MOB 2 will be led by an Air National Guard (ANG) unit. That may be one way to ease the transition. Many ANG pilots fly for commercial carriers, and many of those carriers already operate 767s.

Exact basing decisions will be based on location, capacity, environmental issues, and cost. The USAF plans to table a preferred base and shortlist for the active-duty FTU and MOB 1 in December 2012, so the environmental impact grind can begin and the base can begin receiving aircraft in FY 2016. The ANG-led MOB 2 is expected to get its preferred base and shortlist in spring 2013, and receive aircraft in FY 2018. USAF.

May 8/12: Sub-contractors. BAE Systems announces a contract from Boeing to develop and build the KC-46A’s Actuator Control Unit (ACU), which processes commands to control the aerial refueling boom.

Engineering and development work on the program will be conducted in Endicott, NY with manufacturing at the BAE Systems facility in Ft. Wayne, IN.

March 21 – April 27/12: PDR. Boeing’s KC-46 Tanker completes its Preliminary Design Review (PDR), confirming that it seems to meet system requirements and is ready to proceed with detailed design. In addition to the successful PDR, the Boeing KC-46 team has completed a System Requirements Review, Integrated Baseline Review, a PDR for the base 767-2C freighter, and Firm Configuration Reviews for the 767-2C and the KC-46A Tanker.

The program’s next major milestone is a Critical Design Review that will take place in the summer of 2013, and demonstrate that the KC-46A is ready for manufacture. Boeing.

PDR

March 27/12: Engine contract. Boeing formally signs a contract with Pratt & Whitney’s Military Engines division for up to 368 PW4062 engines (179 planes + 10 spares). It’s a private sub-contract, however, and the parties won’t discuss its value. Suffice to say that the cost of modern jet engines makes this a 10-figure contract, once all engines are ordered.

The 62,000 pound thrust PW4062 is the highest thrust model in Pratt & Whitney’s PW4000-94″ commercial engine family, which powers MD-11, early-model 747, and 767 aircraft. It’s offered for commercial freighter and military tanker applications. Pratt & Whitney.

March 26/12: GAO Report. The US GAO audit office releases report #GAO-12-366, “KC-46 Tanker Aircraft: Acquisition Plans Have Good Features but Contain Schedule Risk.” It cites “broad agreement that KC-46 schedule risk is a concern,” and especially cites overlap among development and production work. The USAF disagrees, citing FAA certification for the First Flight of the baseline 767-2C in June 2014, and promising 60% of FAA certification and military developmental flight testing before Milestone C production approval in August 2015. On the other hand, the GAO has usually been right about these risks, and the USAF has been wrong – most recently in the F-35 program.

Key information has been fed into other parts of this article, but this excerpt deserves especial attention:

“According to program officials, a change in system requirements, although unlikely… could increase the Air Force’s exposure to additional costs… the biggest risk to the KC-46 program is the Department’s ability to minimize changes to the contract… DOD has demonstrated limited ability to maintain stable requirements and limit changes to program technical baselines on previous complex weapon system programs, and that minimizing such change is essential to the success of the KC-46… any engineering or contract changes affecting system requirements or having the potential to impact program cost, schedule, and performance baselines must be approved by the Air Force Service Acquisition Executive in consultation with the Secretary and the Chief of Staff of the Air Force… Program officials maintain that… pricing will likely stay intact as long as the contract is not opened to negotiate modifications. […]

Boeing has to correct any deficiencies in the KC-46 discovered during the development program… on the four development test aircraft and all production aircraft… at no additional cost to the government. In addition, there is a special contract provision that requires each aircraft to demonstrate a certain fuel usage rate before the government accepts the aircraft. If any aircraft burn fuel above this rate, Boeing is required to propose a corrective action at no cost… if Boeing cannot meet the required usage rates, there are contract provisions allowing for a decrease in the amount paid to Boeing.”

March 7/12: Air Mobility Command chief General Raymond Johns at a House Armed Services Committee hearing:

“We continue to execute the program to cost and schedule baselines we established, along with Boeing.”

A Preliminary Design Review is scheduled later this month. Bloomberg.

March 7/12: Basing plans. From the USAF’s FY 2013 Force Structure Changes [PDF]:

The Air Force is currently developing requirements for the first two KC-46 bases, and expects to approve basing criteria in Spring 2012, identify candidate installations in Summer 2012, select preferred and reasonable alternatives by the end of calendar year 2012, and make final decisions in 2013.”

The Air Force expects aircraft deliveries to these first 2 bases in FY16. The next round of basing decisions is planned for FY14 at the earliest.

Feb 13/12: RDT&E budget. The Air Force asks for $1.8 billion in RTDE funds for fiscal year 2013 as part of the President Budget. This would be the peak of planned research and development spending on the program over 2011-2017, at 27% of the total. Air Force budget justification [large PDF].

Air Mobility Command (AMC/CC) has not yet determined an Initial Operational Capability (IOC) date, while Full Operational Capability (FOC) is expected approximately 24 months after IOC. The Air Force schedule as of December 2011 plans to reach Milestone C in Q4 FY15. These plans have been incorporated into the program briefing, above. See next entry below on the various risk assessments made about that schedule.

Jan 17/12: DOT&E doubters. When Airbus lost the contract, they placed 2 markers. One was that Boeing couldn’t deliver to their claimed price, and that has proven true (vid. Nov 27/11 entry), though their bid remains lower than Airbus. The other was that Boeing wouldn’t be able to make the delivery schedule, and the US Defense Department’s Director of Operational Test and Evaluation’s FY 2011 Report adds weight to that belief. The report backs their position up with hard numbers, and bluntly concludes that “the KC-46 test program is not executable.”

To support that claim, DOT&E notes that military testing with past large aircraft averages under 30 flight hours per plane, per month. The Boeing/USAF TEMP schedule plans 42 FHPM, for flights that are “more specialized, higher risk, and more resource-intensive than FAA certification.” Worse, their planned 15% re-fly rate for military test items is even farther off; the 737-derivative P-8A, which is considered to be a successful program, has a current re-fly rate of 45%. Correcting to past averages adds 4 months to the 17-month testing schedule. DOT&E believes that even then, the 750 operational flight test hours aren’t enough, and 1,250 would be more realistic. That takes the testing schedule from 21 to 25 months.

Other serious omissions cited include no time for correction of discrepancies and/or deficiencies discovered during developmental testing, and no provision for the refueling boom control algorithm changes and/or procedural modifications that have been required for other new aerial refuelers. The report doesn’t say so, but the net takeaway is that Boeing is very likely to be late with its promised 2017 delivery. The USAF responded to Gannett’s Air Force Times with partial disagreement:

“The Air Force respects the opinions of the Office of the Director, Operational Test & Evaluation, but does not agree with its assessment that the KC-46 test program is ‘not executable’… The Air Force does acknowledge that Boeing’s overall KC-46 program schedule is considered medium risk, in part due to its aggressive flight-test schedule.”

Jan 4/12: Wichita lineman, farewell. Boeing confirmed it’s going to close its Wichita, KS plant by the end of 2013. Wichita is currently the base for the company’s Global Transport & Executive Systems business, and its B-52 and 767 International Tanker programs. The facility also provides support for flight mission planning and integrated logistics.

Some of the 2,160+ Wichita jobs will be moved; others will be cut, beginning in Q3 2012. The move rankles hard in Kansas, as Boeing touted the jobs and state economic benefits if they won the tanker contract, and secured hard lobbying from state and federal representatives. Who now feel somewhat betrayed. The company counters that it isn’t entirely betraying those promises, as it spent more than $3.2 billion with approximately 475 Kansas suppliers in 2011, making it the 4th largest state in Boeing’s supplier network. That prominence is not expected to change, and the 24 Kansas KC-46A suppliers will still be providing elements of the aircraft as originally planned.

Once the Wichita plant closes, engineering work on the KC-46A will be placed at the Boeing facility in Oklahoma City, OK, instead. Work to convert 767s to KC-46 tankers will now be performed right on the 767 production line in Puget Sound, WA, copying a model first used with the 737-derived P-8A Poseidon sea control aircraft. Future aircraft maintenance, modification and support work will be placed at the Boeing facility in San Antonio, TX, which currently handles KC-135 and KC-10 maintenance and upgrade work. Boeing | NY Times | Congressman Mike Pompeo [R-KS-4, not happy].

Boeing closing its Wichita plant

Nov 27/11: EMD Overage rises again? Maybe. Media reports tout a figure of $500 million over maximum cost, but a breakdown says otherwise. The Pentagon’s latest Selected Acquisition Report reportedly gives a program manager’s estimate of $5.3 billion, which would actually be $1.2 billion over the KC-X EMD phase’s original target cost. Up to $4.9 billion, however, the government pays $600 million more, and Boeing pays $400 million. Costs above that are all Boeing’s responsibility. Boeing’s current estimate is $5.1 billion, which would raise its liability to $600 million (400 + all 200 overage). If the government program manager is right, Boeing’s liability rises to $800 million (400 + all 400 overage), while its overall bid cost to the US government for development plus production remains below Airbus’.

The SAR report in question appears to be an advance copy, as there has been no public release yet. It allegedly says that KC-46A engineering, manufacturing and development are “progressing well with no significant technical issues.” Given the figures above, that must be a relief to Boeing’s management. As for the Pentagon, it doesn’t have to care which EMD Phase figure is correct, since their costs are now known: $4.5 billion ($3.9 billion + $600 million). Above $4.9 billion total split costs, they aren’t paying for anything, and the estimate spread shows that there’s almost no chance of coming in under $4.9 billion. Bloomberg News.

FY 2011

Boeing wins round 2. Interim baseline review. Suppliers and components.

KC-X Options Comparison

KC-X options
(click to view full)

Sept 13/11: Sub-contractors. AmSafe Industries, Inc. announces that it will supply 9g-rated barrier nets, and stationary and movable smoke barriers, specifically designed for the USA’s new KC-46A 767 aerial tankers. AmSafe is a global leader in this sort of technology; they’re also known as the makers of Tarian cloth armor that can stop enemy rockets.

Deliveries of the KC-46A internal barrier systems are expected to begin in 2015, and could be worth more than $45 million for all 179 planned aircraft.

Sept 13/11: Sub-contractors. BAE Systems’ Attendant Control Panel (ACP) for Boeing’s new civilian 737 interior will be migrating to the KC-46A. The touch-screen, networkable panel is designed to control a variety of interior functions such as lighting, drinking water, and waste tanks. Prices were not revealed. Work on the KC-46A tanker touch-screen cabin control systems will be conducted in Johnson City, NY, and Fort Wayne, IN. BAE Systems.

September 2011: Sub-contractors. Vol. 16, #4 [PDF] of Rockwell Collins’ internal Horizons magazine, whose “Refueling Innovation” article discusses their development of the KC-46A’s flight controls and refueling systems.

The stereoscopic Remote Vision System, which will display the refueling operation on both standard and 3-D screens, apparently drew on internal experience that included the Mars Rover, UAVs, and a remotely-operated bomb-disposal robot. Overall, the article cites ruggedization of components, and information fusion from the wide array of sensors and datalinks, as the 2 key engineering challenges. TSAS, which emerged from the latter challenge, is even being tested on Android OS smartphones and tablet computers.

Aug 24/11: IBR. The U.S. Air Force completes an interim baseline review (IBR) for the KC-46A.

IBRs provide mutual understanding of risks inherent in contractors’ performance plans and management systems, and outline what resources are needed to achieve program goals. This IBR had to be complete within 7 months of contract award, which would be Sept 24/11. The next major milestone is the Critical Design Review, which is scheduled to happen by September 2013. Aviation Week.

July 14/11: Politics. Sen. John McCain [R-AZ], the ranking Republican on the Senate Armed Services Committee, sends a letter to the Pentagon that calls Boeing’s KC-X EMD bid “completely unacceptable”. His issue is that any increases between KC-X’s EMD target cost (revealed as $3.9 billion), and the $4.9 billion ceiling cost are split between Boeing (40%) and the USAF (60%). The net result is that Boeing’s lowball bid costs taxpayers an extra $600 million beyond their bid, and Boeing itself $700 million. Even that reported bid price still leaves Boeing lower than Airbus’ overall price, however, which was $2 billion higher for the combined EMD phase and subsequent production of 13 initial jets.

On the other hand, the practice of lowballing bids in order to secure contracts, then raising the real costs afterward, is correctly seen as toxic. The result is grave difficulty in budget planning, as other programs are sacrificed or compromised in order to pay for widespread overcharges.

In fairness to Boeing, it’s worth going back to the original contract bids. Reports right after the February 2011 award had EADS Airbus bidding $3.5 billion for the EMD phase, while Boeing had bid $4.4 billion for the EMD phase alone. That means the USAF knew of about $500 million beyond its target costs from the outset, for an aircraft that had not been fielded or tested yet, and involved more development work than EADS’ offering. That means added risk of future increases, but the swiftness of these cost revisions strongly suggests that they were known beforehand. Actual costs for Boeing’s EMD phase are currently $5.2 billion, and the amount of the cost breach tends to lower confidence in Boeing’s ability to meet the contract schedule, a point that was also raised by Airbus after the award.

The question is whether Sen. McCain’s opposition will have any effect at this point in time. That may seem unlikely, but then, it also seemed unlikely when he opposed the original KC-767 lease deal post-9/11. McCain release | Bloomberg.

June 24/11: Costs. Bloomberg reports that Boeing’s KC-X bid is going to be $300 million over the KC-X cost ceiling, which it reveals as $4.9 billion. Because it’s a fixed-price contract, Boeing is solely responsible for those extra costs.

According to Bloomberg, a USAF statement from Lt. Col. Jack Miller said that the USAF was told after the contract award that: “it proposed a ceiling price that is less than its actual projected cost to execute the contract… There is no legal barrier that prohibits pursuing a below-cost proposal strategy and Boeing’s met all rules.”

Recall that the Feb 24/11 contract award said only that Boeing’s Engineering & Manufacturing Development (EMD) phase contract was “over $3.5 billion.” Subsequent reports had Boeing’s EMD phase bid at $4.4 billion, vs. EADS Airbus’ $3.5 billion. On the other hand, the total bids for EMD + 4 planes, and another 14 planes of initial production, was reportedly $20.6 billion for Boeing, vs. $22.6 billion for Airbus – who called Boeing’s bid an “extreme lowball.” If Bloomberg’s report is true, we now have an idea what Boeing was willing to pay, in order to prevent Airbus from setting up a production line in America, and to keep the 767 alive as a military export and commercial option.

June 22/11: After months of refusing to divulge details, Boeing announces major suppliers for its KC-46A team, and confirms the tanker’s fuel capacity at 212,000 pounds, with an offload rate of 1,200 gallons per minute. The KC-46 Tanker team will include more than 800 suppliers in more than 40 states and support approximately 50,000 total U.S. jobs. Major suppliers have been added to the article’s industrial teams section.

June 19/11: Sub-contractors. Raytheon announces orders from Boeing supply digital radar warning receivers, and digital anti-jam GPS receivers, for the KC-46 tanker. Its AN/ALR-69A is an all-digital radar warning receiver designed to work with both fighters and large aircraft, and its technical architecture will speed up signal identification amidst cluttered environments.

The digital anti-jam GPS receiver, with its multielement controlled reception pattern antenna, integrates both reception and high performance digital anti-jam capabilities into a single product.

June 18/11: Sub-contractors. Eaton Corp. announces a Memorandum of Agreement with Boeing to supply hydraulic and fuel distribution subcomponents, cargo door electro-mechanical actuation systems, hydraulic system components, electrical sensing and control devices, and cockpit controls over the life of the KC-46A program.

June 7/11: KC-46A details emerge. Flight International reveals more about the KC-46A, while outlining what we still don’t know, 3 months after one of the largest contracts in USAF history.

For starters, it’s based on a cargo variant. At over 188,000 kg/ 414,470 pounds, the 767-2C’s maximum takeoff weight is about 20,000 pounds heavier than the 767-200ER, making it even heavier than the stretched 767-300ER that Boeing rejected for Round 1. The 2C is slightly stretched itself, at 6.5 feet longer than the 200ER, with a cargo floor and door. Beyond this, the winglets, 787-based cockpit large display system, auxiliary fuel tanks and provisions for tanker systems, and more powerful Pratt & Whitney 4062 turbofans are all known changes from the 200ER.

To find out if Boeing has made any other changes from the basic 767-200ER, outsiders will reportedly have to wait until Boeing completes a USAF system requirements review, and an integrated baseline review.

May 6/11: Sub-contractors. Marshall Aerospace announces that they had been picked in 2010 to supply the KC-46A’s integrated Body Fuel Tanks, and that Boeing’s win has resulted in an initial contract for the design, certification and manufacture of an initial batch of development tanks. They expect production orders for “more than 650” tanks to follow over a 15 year period, in order to equip the KC-X program’s 179 aircraft, with a total value exceeding GBP 100 million.

Marshall Aerospace has previous experience producing integrated Body Fuel Tanks for Boeing, including the 747, 777, and the 737-derivative P-8A Poseidon programs. Boeing has refused to discuss its Round 2 partners, but Marshall appears to have elbowed Round 1 partner Sargent Fletcher aside for this role.

March 11/11: Aviation Week outlines what we still don’t know about the KC-46A. We still don’t know the actual development phase price. We still don’t know the plane’s configuration, either, which makes it impossible to evaluate the likelihood that Boeing can deliver on time. Excerpts:

“Neither the U.S. Air Force nor Boeing have stated what exactly “over $3.5 billion” means for the KC-46A development contract… [Boeing tanker VP Jean] Chamberlain acknowledged on the company’s Feb. 24 telecon post-win that this is “concurrent development” meaning flight test and developmental activities are taking place as the first aircraft are being built…Thanks to the three-time restructured F-35 development program, the term “concurrent development” has become a bit of a dirty word among some in Pentagon circles… There are a few things we do know: Somehow Boeing is putting a digital 787 cockpit into an analog 767 aircraft and there is a modified KC-10 boom to meet the gallon-per-minute offload requirement. But, we don’t know what the design entails in terms of risk reduction on the platform or on the mission systems. Finally, we don’t even know officially that work has begun on this contract. Neither USAF nor Boeing will confirm.”

March 4/11: No protest. EADS North America chairman Ralph Crosby expresses disappointment at the press conference, but says that EADS could not have undercut that “extremely lowball bid,” submitted to keep Airbus from securing a US production site. The company “will not take any action that could further delay the already overdue replacement of the Air Force’s aging tanker fleet… Much is promised by our competitor, whom we congratulate. However, should they fail to deliver, we stand ready to step in with a proven and operating tanker.”

More precise figures come from the US AFA’s report of the conference:

“…Crosby revealed – based on an hour-long debrief from the Air Force last week – that the price difference between the companies’ bids was 10 percent. Boeing bid $20.6 billion and EADS $22.6 billion on initial development and initial production of their respective KC-46A and KC-45 tankers… He expressed doubt that Boeing will be able to deliver all 18 aircraft by 2017 as called for… because Boeing will not have its first flight-test-worthy KC-46A ready until 2015. [Crosby] also revealed that EADS’ estimated cost for engineering and manufacturing development on the KC-45 – which the company would have modestly revised from the existing design – was $3.5 billion, while Boeing bid $4.4 billion for EMD on its design, which has not flown.”

The fixed price contract means that if Boeing fails to deliver, most of the financial risk is theirs. That leaves the USAF with the operational risk, if they can’t hold Boeing to its performance commitments. Read: EADS North America | Reuters | US Air Force Association | Warner Robins Patriot.

March 3/11: Flight International:

“Newspaper Les Echos published a small article four days after the contract award noting that the USAF’s decision on tankers will make it “very difficult” for Paris to purchase the General Atomics MQ-9 Reaper unmanned air vehicle, which is competing against the EADS Talarion and a Dassault/Thales/Indra consortium offering the Israel Aerospace Industries Heron TP.”

The French do make another choice, at first, but costs and delivery times eventually do force them back to the MQ-9. See “Apres Harfang: France’s Next High-End UAV” for full coverage.

Feb 28/11 – March 1/11: Debriefing session with EADS North America. Meanwhile, the government and Northrop Grumman/EADS still have not reached a legal agreement on the canceled KC-45 contract. Aviation Week.

KC-46A & F-35

KC-46A concept
(click to view full)

Feb 24/11: Boeing wins Round 2. The “KC-46A” win surprises many aerospace analysts, who expected an EADS win based on leaks that EADS had scored better in the USAF’s models, and expectations they could price their planes lower. The Pentagons says that both candidate aircraft met all required criteria, but Boeing’s adjusted price was over 1% less than Airbus’. That meant the USAF did not consider various “non-mandatory” bonus criteria, which could only have made a difference of up to 1%.

Note that these are adjusted prices. Rep. Norm Dicks [D-WA], for example, claims credit for successful pressure to change the USAF’s costing model from 25 years of expected fuel costs to 40 years, which he boasts cost Airbus “billions of dollars” in the respective calculations.

As a result, Boeing in Seattle, WA receives a fixed price incentive firm contract valued at “over $3.5 billion” for the KC-X Engineering and Manufacturing Development phase, which will deliver 18 of their KC-46A aircraft by 2017. The ASC/WKK at Wright Patterson AFB, OH, will manage this contract (FA8625-11-C600). A newly opened assembly line in Everett, WA will build the tankers, including all the military modifications to the airframe, right alongside commercial 767 airliners, rather than shipping 767s elsewhere for military modifications. This approach was pioneered by the 737-based P-8A Poseidon sea control aircraft program, and will now be extended to the KC-46A.

By comparison, the Feb 29/08 award to EADS & Northrop Grumman (FA8625-08-C-6451) would have involved 4 test KC-45 aircraft for $1.5 billion, plus 5 production options for up to 64 aircraft at up to $10.6 billion. Over 18 aircraft, that leads to a “base plus averaged” total of $3.819 billion. US DoD | Boeing release | Boeing feature w. video | EADS North America || Agence France Presse | Bloomberg | Chicago Mag | CNBC | DoD Buzz | Defense News | Flight International | Seattle Post Intelligencer.

Boeing wins KC-X EMD with 767-based KC-46A

Feb 14/11: The Pentagon releases its FY 2012 budget request, which includes $877.1 million in development funding for the KC-X program. The FY 2011 request for $863.9 million is still in play as well, however, thanks to the 111th Congress’ failure to pass a FY 2011 budget.

The 112th session of Congress is dealing with the FY 2011 budget as H.R. 1, and could explicitly delete KC-X funding if its disagreements with the USAF run deep enough. The other option would be more passive, and involves continuing all FY 2011 spending at FY 2010 levels. A “2010 Redux” option would be a problem for KC-X, because that would give the program just $14.9 million to work with. On the other hand, a passive approach by Congress would allow to USAF to “reprogram” some funds from elsewhere into KC-X, whereas an explicit rejection would not.

Feb 10/11: Final Bids. Boeing and Airbus delivery their final KC-X bids. Airbus | Boeing | Flight International.

Final bids

Feb 8/11: Turbulence ahead for EADS. The Frankfurter Allgemeine Zeitung reports that Daimler plans to sell its stake in EADS when a consortium agreement expires in June 2012, in order to focus on its car manufacturing business. If they do, the move will have large ripple effects, which is why the news has provoked meetings at the highest levels of Germany’s government.

Daimler already dropped its stake in EADS from 22.5% to 15%, in a 2007 deal brokered by the government with a German bank consortium. Germany has since tried but failed to find a long-term German investor to take over the banks’ 7.5% stake, in order to keep the long term German-French shareholder balance at 22.5% each. The banks agreed to extend the current arrangement to 2013, and France’s Lagardere media group is looking to sell its own 7.5% stake at some point after 2012, but Daimler’s planned departure revives that issue of shareholder balance as a near-crisis. A German replacement firm with deep enough pockets, technical expertise, and enough of an interest in aerospace may not exist. Deutsche Welle.

Jan 31/11: WTO on Boeing. The World Trade Organization releases preliminary information its decision re: Boeing subsidies (DS 353), the other end of the trade dispute that has already seen a ruling concerning Airbus. The release took place to the 2 companies. A full public report will not be available for a couple of weeks – which matters, because accounts differ.

Boeing implies that the WTO rejected most claims, leaving only $2.6 billion in subsidies. They contrast this with the June 2010 decision that found $20.4 million in illegal Airbus subsidies: $15 billion in launch aid, $2.2 billion in equity infusions, $1.7 billion in infrastructure, and roughly $1.5 billion in R&D support, with $4 billion in illegal launch subsidies that must be restructured.

Airbus, in contrast, points to $5 billion of illegal subsidies to Boeing in this decision, with additional figures to be determined in later stages of this dispute, plus over $2 billion in illegal state and local subsidies that Boeing will receive in the future, and an expected WTO ruling that Washington State and the City of Everett must stop subsidizing Boeing. Airbus adds that they believe the WTO will find that Boeing subsidies were more distorting than Airbus’ loans, and float a $45 billion damages figure. Time will tell, but this sentence in Airbus’ statement is certainly clear:

“Taking the cases together, the WTO will be seen to now have specifically green-lighted the continued use of loans in Europe and commanded Boeing to end its illegal R&D cash support from NASA, DoD and the US taxpayers.”

Look for this case to continue, though the emergence of competitors in Russia and China could lead to negotiations, in hopes of setting global standards around subsidies. WTO DS 353 | Airbus | Boeing | Boeing WTO mini-site | Flight International | NY Times | Seattle Post-Intelligencer. See also Sept 15/10 entry.

WTO ruling on Boeing unfair subsidies

Jan 27/11: Italy. The Italian Air Force’s accepts the 1st of 4 delayed Boeing KC-767A tankers at Pratica di Mare AB near Rome. This KC-767 is registered as MM 62229, and will now enter a series of evaluations and other activities before being placed into operational use. There have been a number of issues with Italy’s tankers, so their acceptance is important to Boeing. Flight International.

Jan 19/11: During in-flight testing between an EADS MRTT tanker plane destined for Australia’s RAAF, and a Portuguese air force F-16 fighter, the refueling boom loses 1 of its 2 stabilising fins, making the device uncontrollable. The incident resulted in the detachment and partial loss of the refuelling boom from the MRTT, and the pieces fell into the sea. Fortunately, the plane itself made it back in one piece.

Airbus is investigating the mishap, and at least they have a flying platform to test, but the timing could hardly be worse. Australian DoD | Flight International | Reuters.

A330 refueling accident

KC-30B & F-16s

KC-30 & F-16s
(click to view full)

Dec 13/10: Team EADS. Britain’s 1st A330 MRTT performs the type’s 1st fuselage-mounted hose-and-drogue aerial refueling dry contacts, using an F/A-18 Hornet fighter. Airbus Military. The 1st wet refueling took place on Jan 21/11, transferring over 6 tonnes of fuel at an altitude of around 15,000 feet, and at speeds from 250 – 325kt. AirTanker.

Cobham’s belly-mounted 805E FRU (Fuselage Refueling Unit) is part of the proposed USAF KC-45’s 4-point refueling system, which shares the 2 removable digital underwing hose-and-drogue refueling pods with FSTA aircraft, but also adds a fly-by-wire ARBS boom for UARRSI dorsal receptacles. Both the belly-mounted FRU and underwing hose-and-drogue refueling pods share the same modular architecture, and all 4 systems are controlled from the Remote Aerial Refueling Operator (RARO) console in the cockpit.

Dec 1/10: Delay. USAF Lt. Gen. Mark Shackelford, the military deputy from the Office of the Assistant Secretary of the Air Force for Acquisition says that the final KC-X award will take until 2011, instead of being announced in November 2010. The USAF release adds:

“Air Force officials have said the KC-X source selection process will continue despite a mistake in November, where a limited amount of identical source selection information was provided to both KC-X offerors concerning their competitor’s offering… The information concerned was limited to a single page of non-proprietary data on a CD that did not include any offeror-proposed prices… Air Force officials have analyzed the information that was actually accessed by one of the offerors and have taken steps to ensure that both competitors have equal access to this information.”

Nov 21/10: Breach. A USAF error sends the wrong documents back to EADS and Boeing, giving them material from the other firm’s bid, The data sent by computer disk reportedly included pricing information, and both sides did the right thing and contacted the USAF immediately. Defense News | The Telegraph.

Protoccol breach

Oct 19/10: Tanker analysis. Iris Independent Research releases their KC-X competition white paper, “9 Secrets of the Tanker War.” One entirely unsurprising conclusion: KC-X’s 179 planes are it, and there will be no similar-sized KC-Y or KC-Z buys for at least 2 decades, if ever.

Given demographic and fiscal realities in the USA, that strikes us as a very safe prediction. Iris release | Full paper [PDF] | DoD Buzz.

Oct 6/10: No Antonov. The US GAO dismisses US Aerospace’s KC-X protest, leaving just Boeing and EADS. The core of the decision revolves around whether the bid was late, hence ineligible. The ruling that it was late offers an effective primer on bid delivery planning:

“In partially dismissing USAI’s protest, we concluded that, while many of USAI’s complaints were potentially relevant to the protester’s proposition that its messenger was understandably confused as to the location for submitting USAI’s proposal, such complaints did not support USAI’s allegations of intentional agency misconduct… it was USAI’s decision – not that of the Air Force – to have its messenger arrive at Wright-Patterson AFB entry gate 19B with less than an hour remaining before proposals were due; it was USAI’s decision not to seek advance agency approval for its messenger to be admitted to the AFB; and it was USAI’s decision not to confirm in advance the precise location of, and directions to, the building at which proposals were to be received. Based on our review of the protest allegations and the record submitted, we concluded that USAI’s allegations of intentional agency misconduct were insufficient to warrant further consideration…”

See: GAO statement | GAO B-403464 decision | Washington Post.

Oct 6/10: Team EADS. Airbus Military obtains A330 MRTT military certification from Spain’s Instituto Nacional de Tecnologia Aerospacial (INTA), which follows the European Aviation Safety Agency’s (EASA) civil Supplemental Type Certificate (STC) awarded earlier in 2010. The first 2 A330 MRTTs conducted more than 280 flights as part of the certification process, in addition to another 170 by A310 demonstrator aircraft.

As one can see by the number of flights involved, certification is an under-appreciated roadblock in the military delivery process. Fortunately certification in one jurisdiction makes subsequent certifications either much easier or unnecessary, depending on a jurisdiction’s standards and decisions. The INTA certification clears the way for Airbus Military to deliver Australia’s KC-30As, later in 2010, but the USAF would insist on its own certification process. Airbus Military | Agence France Presse | Australian Aviation | The Australian | Le Figaro [in French] | Seattle Post-Intelligencer.

FY 2010

Round 2 RFP and bids. WTO dispute.

AN-70

AN-70
(click to view full)

Sept 15/10: Early reports leak out that the WTO is about to find that Boeing’s aircraft have also been the recipients of illegal subsidies. Since Boeing had been pushing the subsidy point hard in Congressional debates, a finding of that sort would be significant. It will certainly make for a more difficult argument on Boeing’s part, both because the political argument becomes less clear, and because the USAF’s decision to exclude WTO issues from the competition becomes more defensible. Boeing remains on the offensive, arguing that:

“If today’s reports are accurate that some $3 billion of the EU’s claims were upheld by the WTO… the ruling… confirms that European launch aid to Airbus stands as the single largest and most flagrant illegal subsidy in the aerospace industry. Nothing in today’s public reports on the European case against the U.S. even begins to compare to the $20 billion in illegal subsidies that the WTO found last June that Airbus/EADS has received (comprised of $15 billion in launch aid, $2.2 billion in equity infusions, $1.7 billion in infrastructure, and roughly $1.5 billion in targeted research support). Nor are there seemingly any violations requiring remedy approaching the scale of remedy required of Airbus/EADS… Neither do the public reports suggest that Boeing’s traditional market based approach to financing new aircraft development will need to change; a distinct contrast…”

WTO cases DS 353 (vs. Boeing) and DS 316 (vs. Airbus) | Boeing | EADS North America | European Union | Agence France Presse | The Australian | Bloomberg | India’s Economic Times | Reuters | London Telegraph | UPI.

Sept 14/10: Team EADS. A pair of Australian KC-30A tankers hook up and transfer fuel at 1,200 gallons per minute through the A330’s boom. That figure meets the USAF’s maximum requirement, something Boeing has yet to do in the air. EADS North America Chairman Ralph D. Crosby, Jr. also went on the offensive with regard to fuel economy:

“In any likely Air Force operational scenario, Boeing’s concept tanker will cost 15% to 44% more, measured on the basis of fuel burned per gallon of fuel delivered.”

See: EADS KC-45 Now | Seattle Post-Intelligencer.

Aug 4/10: No Antonov. US Aerospace/ Antonov is disqualified for late submission. Aviation Week quotes Pentagon press secretary Geoff Morrell:

“The proposal was late and by law we are not allowed to consider it. We are considering two proposals and U.S. Aerospace is not one of those being considered.”

The magazine adds that:

“According to an industry executive, the company’s messenger arrived at the Wright-Patterson AFB gate at 1:30 p.m. July 9 (30 minutes before the deadline) and was denied entry, given bad directions and told to wait by Air Force personnel. As a result, the Air Force stamped the proposal received at 2:05 p.m.”

On Aug 2/10, U.S. Aerospace filed a bid protest with the Congressional Government Accountability Office, citing “unreasonable” conduct by the USAF. The firm’s bid had reportedly revolved around an “AN-112” based on the 4-engine AN-70 turboprop transport.

July 13/10: Team EADS. The Hill reports that the KC-X bid cost EADS North America $75,000 in final printing costs alone.

July 9/10: Team Boeing. Boeing delivers its KC-X v2.0 bid. Its release mentions that its design will contain cockpit displays from the 787 Dreamliner, which may not be a change from the first round.

July 9/10: Antonov?!? US Aerospace announces that it has submitted a joint KC-X bid with Antonov at $150 million per plane, following SEC notification of an agreement with Antonov and intent to bid on July 1/10. That agreement would give US Aerospace lead contractor status and final American assembly rights only under a KC-X contract, while Antonov would be the technical lead and manufacture components.

Unlike the March 19-22/10 UAC/ IL-96 hoax, this report has much more backing behind its assertion of a bid. The question is whether it makes any more sense, or would even qualify under Round 2’s mandatory criteria. Reports indicate a bid based on the modernized AN-124-100 “Ruslan” super-heavy transport, which would offer heavy airlift options that beat the C-17 hollow, but terrible operating efficiency as an aerial tanker. Reports of a custom designed “AN-112” make even less sense, given the years-long development and certification timelines. Unlike Ilyushin, Antonov doesn’t even have a base civilian airframe in the right size category. Defense News may have the answer that explains the hype:

“…a May 24 SEC report filed by U.S. Aerospace signals it is in financial trouble. A number of factors “raise substantial doubt about the company’s ability to continue as a going concern,” the firm told federal regulators.”

See: US Aerospace re: bid submission | US Aerospace re: agreement | Defense News | The DEW Line | UPI.

July 8/10: Team EADS. EADS North America delivers its KC-X v2.0 bid, one day before the extended deadline, and highlights key members of its Round 2 industrial team. EADS.

July 8/10: WTO. The World Trade Organization has put off a ruling on the EU’s subsidy complaint against Boeing (case DS 316) from July 16/10 until mid-September 2010. As the Wall Street Journal put it: “While the panel is likely to find that the U.S. has provided improper subsidies, it isn’t known if the WTO will be as severe on Boeing as it was on Airbus.” Meanwhile, the delay leave EADS very exposed in the political battles over the US KC-X contract. The EU is unhappy:

“The time lag between this case, and the United States’ case against support to Airbus (DS 316) has constantly increased over the six years this dispute has been running and the gap is now at nearly a year. It creates the wrong impression that Airbus has received some WTO incompatible support, whereas Boeing has not. Only when we have received both panel reports will both sides have a more complete picture of the dispute… We now expect the Panel to issue its interim report in DS 353 without any further delay.”

EADS Airbus’ CEO Tom Enders said he was “surprised and disappointed” by “the last minute announcement of yet another delay,” and appears to question the capability of the WTO to play a meaningful role in the global trade order:

“We have said time and again that the complexity, interconnectedness and industrial significance of the Boeing and Airbus cases would strain the capabilities of the WTO. Since these cases were filed, the world has changed. In aviation, the previous duopoly marketplace is increasingly being populated by government-sponsored players, leaving Boeing and Airbus as those that, by any objective measure, benefit least from government support. The ongoing struggle of the WTO to address the world as it was in 2004 (the date the cases were filed) raises the question whether it can succeed in its basic mission to create a climate for a negotiated settlement on the basis of fair market rules in the interest of both the industry and the employees on both sides of the Atlantic.”

See: WTO cases DS 316 and DS 353 | EU release | Airbus release | Agence France Presse | India’s Business Standard | Seattle Post-Intelligencer | UK’s Telegraph.

June 30/10: WTO. Boeing hails the public release of a World Trade Organization ruling on Airbus subsidies (case DS 317), which will be a lobbying point in the current KC-X competition. Airbus has its own take, of course, and the WTO also has a case involving Boeing – but it hasn’t ruled on that one yet. A columnist in Boeing’s hometown of Everett, Washington even thinks the ruling could ultimately help both Boeing and Airbus, which have seen state-owned competitors enter the marketplace in recent years. WTO | Boeing | Airbus | Everett Herald op-ed.

WTO ruling on Airbus unfair subsidies

June 7/10: WTO. Boeing teams with AgustaWestland in the US Presidential Helicopter competition. Finmeccanica’s subsidiary has produced several Boeing helicopters under license in England and Italy (WAH-64 Apache, CH-47 Chinooks), and now Boeing will return the compliment with the AW101. The license will give Boeing full intellectual property, data and production rights, making its version of a Presidential AW101 bid a Boeing aircraft, built by Boeing personnel, at one of its U.S. facilities. This decision is likely to create several ripples. Loren Thompson of the Lexington Institute points out that:

“Boeing’s bid could create some embarrassing moments for both itself and Lockheed Martin. Lockheed Martin spent years arguing that the AgustaWestland airframe was superior… By the same token, Boeing is engaged in a bitter dispute with Airbus concerning European aircraft subsidies, and [the AW101 has received them]…”

See: Boeing | Finmeccanica [PDF] | AgustaWestland | DoD Buzz | Lexington Institute.

June 7/10: Team Boeing. Finmeccanica subsidiary DRS announces a teaming agreement with Boeing for work on its KC-X “NewGen Tanker” offering. DRS will collaborate with Boeing on the console design and then manufacture the Aerial Refueling Operator Station (AROS), and will also provide the interconnect design and associated cable sets to integrate AROS into the Tanker. All this is contingent on a contract win, of course.

June 3/10: Team EADS. EADS says it has American partners for its KC-X bid, but won’t name them “because we don’t want to put them under pressure.” Defense News.

May 19/10: The House Armed Services Committee takes the first step toward introducing WTO subsidy rulings to the competition, as part of its recommended FY 11 defense budget (H.R.5136). The modified bill reportedly requires the Pentagon to submit an interim report, discussing the impact of government subsidies on the KC-X competition, at the instigation of Rep. Adam Smith [D-WA]. The implicit message in that name is lost on nobody. See: Congressional Quarterly | The Hill | Politico | bNet op-ed.

May 13/10: U.S. Senator Sam Brownback [R-KS] and Congressman Todd Tiahrt [R-KS] hold a bi-partisan press conference announcing the introduction of the bi-cameral Fair Defense Competition Act (H.R.5298 and S.3361). The bill attracts 39 co-sponsors in the House, and its Senate counterpart attracts 3.

These bills would require the Department of Defense to consider World Trade Organization (WTO) decisions for military acquisitions. Specifically, they would require the Pentagon to add the cost of illegal subsidies onto the price of a competitor’s bid proposal, following a ruling by the WTO. The WTO has already ruled that Airbus’ aircraft were built using illegal subsidies. A ruling on Airbus’ complaint concerning Boeing is pending, but would not come in time to affect the KC-X competition.

The Seattle Post-Intelligencer says that Boeing lobbyists have been lining up legislators for these measures, and Boeing itself is making rather unlikely noises about not bidding over subsidy-related issues. See also: Defense News | ABC affiliate KAKE-10 | US NPR | Reuters | Seattle Post-Intelligencer.

May 12/10: Team Boeing. Rockwell Collins announces that it is part of Boeing’s Round 2 aerial tanker team, with negotiated terms to deliver the same flight deck technology it supplies for the 787 Dreamliner, along with the KC-767’s Communication, Navigation, Surveillance/Air Traffic Management (CNS/ATM) systems, aircraft networks, and other electronics.

May 8/10: A Minneapolis Star Tribune article provides a glimpse into Boeing’s PR offensive on the ground. Part of it involves a trailer with simulators for the KC-767’s new boom, and associated fighters, for some members of the public.

[youtube:http://www.youtube.com/watch?v=SLgMM32LJxg]

Ralph Crosby, EADS NA
click to play video

April 20/10: EADS back in. EADS North America announces that it intends to submit a proposal for the KC-X aerial tanker RFP based on the KC-45 tanker, a version of the A330 MRTT/ KC-30B design that won the original contract. The US unit of the European aerospace giant plans to submit the proposal on July 9/10, the last day of the Pentagon’s extended deadline.

The company said it is continuing discussions with potential US partners, but apparently the European defense firm is willing to go it alone, if need be. The company reiterated its earlier promise to build a Mobile, AL manufacturing line for global A330F sales, and KC-X finishing work, if it gets the contract.

April 1/10: Boeing issues statement critical of Pentagon’s decision to extend the RFP deadline if EADS agrees to bid:

“We are deeply disappointed with EADS-Airbus efforts to further delay this vital warfighting program and tilt the U.S. procurement process in its favor. EADS-Airbus has been fully engaged in the competition for four years and was always expected to provide the vast majority of its team’s work content…We do not see a legitimate reason for EADS’s bid deadline extension request, and we believe an extension that favors any individual competitor does not further the goal of ensuring fair competition.”

March 31/10: A group of US senators sends a letter to President Obama criticizing EADS Airbus division for receiving “billions of dollars in illegal subsidies.” The senators urge the president not to extend the KC-X RFP deadline:

“Finally, having relied on illegal subsidies to buy market share in the commercial aerospace market, Airbus now seems intent on further using subsidized aircraft to significantly increase its present in the U.S. defense market. This is unacceptable. We urge you to move forward on the Air Force tanker competition without delay.”

The letter was signed by US Sens. Patty Murray (D-WA), Sam Brownback (R-KS), Chris Dodd (D-CT), Debbie Stabenow (D-MI), Maria Cantwell (D-WA), Lindsey Graham (R-SC), Claire McCaskill (D-MO), and Michael Bennet (D-CO).

March 31/10: Bid extension. The Pentagon announces that if EADS wishes to bid, they will grant a 60-day extension instead of the 90 days requested. This would move the deadline from May 10/10 to July 9/10. Pentagon Press Secretary Geoff Morrell also said that:

“Given that this plane is long overdue, and we do not want its delivery date to slip later than it already has, we are prepared to compress our bid evaluation period to stay as close to the original award schedule as possible so as to still award the contract early this fall… [but we have no] willingness to change any of the plane’s military requirements or the way bids will be evaluated.”

Boeing and some of its supporters in Congress group of US senators criticized the decision. Boeing statement | US Senators’ letter to President Obama (Seattle PI blog) | DoD statement | Reuters

March 22/10: Russians. A Reuters report suggests that John Kirkland, the Los Angeles-based attorney who told various news media that UAC would announce a joint venture and enter the bidding for KC-X, may have been the victim of a scam.

Kirkland sent Reuters copies of letters on what appeared to be letters on “OOO UAC” letterhead, saying that high-level Russian approval of a bid was imminent, but subsequent examination showed contained several grammatical mistakes in Russian. UAC vice-president Alexander Tulyakov drove the final stake in when he told Reuters that:

“John Kirkland is not a UAC representative and we have had no communications with him… We have had no discussions whatsoever with any party about the possibility of producing air tankers for the U.S. air force.”

March 19/10: EADS in, Russians in?!? EADS requests a 3-month extension of the May 10/10 bidding deadline, because it is re-considering a bid submission without Northrop Grumman. The firm’s main foothold in the American market is its successful UH-72A LUH helicopter program, but without an established A330F production line, EADS had previously considered its American base too shallow to handle a contract this big. The Pentagon is reportedly receptive to a bid extension, citing previous examples like BAMS UAV, VH-71 helicopter, Small Diameter Bomb (SDB) II, and LOGCAP IV, among others.

The same day, Russia’s state-owned United Aircraft Corp. reportedly drops a double-surprise. The first surprise is that the firm is supposedly set to sign a joint venture with a small American aerospace firm to market Russian-designed aircraft, including promises that the JV will be announced on March 22/10.

The second surprise is that the firm reportedly intends to bid a tanker version of its IL-96 4-engined, wide body jetliner for the KC-X competition. The IL-96 is civil certified, and can be fitted with Pratt & Whitney engines, but it faces significant disadvantages, despite a price tag that could be as low as half that of a base 767 or A330 airframe. The most prominent obstacle is that the key partner is a state-owned Russian firm. While relations are better than they were in Cold War days, the USA is a long way from trusting Russia as any sort of reliable ally – and the reverse is also true. Congressional opposition to any win would be measured on the Richter scale. Other issues include expected higher operating costs from a 4-engine jet, the low esteem in which Russian airliners are held, and the fact that under 50 IL-96s have been built so far.

Given the expected $100 million cost of a bid, the effort would appear to be quixotic at best, unless the USAF changes it mind and decides to reimburse bid costs. Aviation Week | Bloomberg | Chicago Tribune | CNN | Deutsche Welle | The Hill | McClatchy Newspapers | Politico | Pravda | Reuters | Seattle Times | Wall St. Journal | Washington Post.

March 11/10: As one might expect, political rumbles continue across the Atlantic, with veiled and not-so-veiled threats of a trade war, or retaliation in the defense field. EU release | Aviation Week Ares roundup | Defense News.

March 11/10: EADS out. Aviation Week reports that EADS did not feel confident enough yet in its American footprint, to bid for the KC-X project. Its main beachhead in the USA at the moment is the $3.5 billion UH-72A Lakota Light Utility Helicopter program, which is going well but is an order of magnitude smaller than KC-X.

March 11/10: Team Boeing. Spirit AeroSystems Holdings, Inc. announces that they’ve come to terms as part of Boeing Round 2 KC-767 NewGen Tanker Supplier Team. Upon a contract award from the United States government to Boeing, Spirit will build the Boeing tanker’s forward fuselage section in Wichita, KS.

March 8/10: NGC out. Northrop Grumman has apparently bowed out of the KC-X v2.0 RFP, leaving Boeing as the only bidder. The move is not unexpected, given the requirements and the estimated $100 million cost to bid, but it will create longer-term political issues for the program. The European Union is already issuing rumbles about protectionism, and an early blast from Sen. Sessions [R-AL] may be indicative on the domestic front:

“The unjustifiable overhaul of the Request for Proposals – which went far beyond the narrow problems raised by the GAO – completely abandoned the idea of a game-changing tanker in favor of a smaller, less capable plane. Of the 14 major changes to the solicitation, 12 favored Boeing’s smaller, older aircraft. In the end, the process was skewed, and no one can fault a private company for declining to participate in a government competition engineered to guarantee its failure… American taxpayers… could now be on the hook for the most expensive sole-source contract in history.”

Deputy Secretary of Defense William Lynn said the Pentagon was disappointed, but does not intend to change course. Boeing’s ardent backer Rep. Norm Dicks [D-WA], soon to be head of the House Appropriations’ defense sub-committee, advocates scrapping the bidding process now and negotiating a contract directly, while suggesting an increase in production from the program’s 15 KC-767s per year to 20-25 tankers per year. Northrop Grumman statement | EADS statement | Aviation Week | DoD Buzz | Miami Herald | Politico | Seattle Times | Washington Post early report | Agence France Presse early report | UK’s Daily Telegraph | Sydney Morning Herald | Seattle Post-Intelligencer reactions roundup.

March 5/10: Team Boeing. Boeing announces its RFP v2.0 offering. The new 767 “NextGen” aircraft add a modified version of the new 787 Dreamliner’s flight deck, with its larger displays and other design improvements. Engines will still be Pratt & Whitney’s PW4062s, but the fly-by-wire refueling boom looks different, and so do the wings. Aviation Week attempted to clear up Boeing’s exact offering, but:

“Boeing officials declined to comment on whether the wings, the doors and floors and flaps were being pulled from other commercial models [DID: as in the previous KC-X entry]. They declined interview requests as well…”

The 3rd thing Boeing’s official release emphasized was a pointed reference to the flight control computers that may have been a major cause of Air France Flight 447’s A330 crash over the Atlantic in 2009, with all hands lost:

“The Boeing NewGen Tanker will be controlled by the aircrew, which has unrestricted access to the full flight envelope for threat avoidance at any time, rather than allowing computer software to limit combat maneuverability.”

See also: Boeing | Pratt & Whitney | Aviation Week | DoD Buzz.

Feb 24/10: Final KC-X v2.0 RFP is out. Most of the changes made were narrow and technical, and do not change the structure of the competition. The need for a microwave landing system was scrapped, and Large Aircraft Infrared Countermeasures missile defense systems will now be provided by the government as a separate item, certain items had specifications defined more tightly, etc. Proposals will be due within 75 days of the request, and there will be another 120 days after that for government evaluation.

Price remains the key factor, based on the draft proposal’s weighting system. The development contract is a fixed price incentive deal, with the contractor responsible for 40% of any overruns up to 125% of the contract value, and all overruns beyond that. Production lots 1-2 are fixed price. Lots 3-5 will see a new price negotiated, with the contractor responsible for only the first 2.5% of price inflation. Re-negotiation would happen again for Lots 6-13, but this time the contractor would only be responsible for the first 1% of price inflation.

While these provisions protect manufacturers from spiraling commodity costs, they also allow the USAF to make changes later, so long as they’re willing to pay for them. RFP solicitation on FedBizOpps | US DoD press release | DoD presentation [PDF] | Boeing statement | Northrop-Grumman statement | Seattle Post-Intelligencer rounds up politician reactions in USA | AvWeek reports that NGC is “96-98% unlikely” to bid | Aviation Week article collection | Gannett’s Air Force Times | Government Executive magazine | Miami Herald | Washington Post | Reuters: tanker chronology.

Final KC-X v2.0 RFP

Feb 22/10: Dual buy? Flight International’s Stephen Trimble looks for clues to the funding behind a new lobby group called “Build Them Both.” As one might guess, the group favors a dual-source, accelerated buy contract for the KC-X competition, with both firms receiving contracts but annual orders being determined by production readiness, pricing, and the needs of specific theaters. This was the essence of the late Rep. John Murtha’s position.

Feb 8/10: Dual buy? House Appropriations Defense subcommittee chair John Murtha [D-PA], Capitol Hill’s #1 proponent of a KC-X split buy, dies of complications associated with intestinal surgery. A Washington Post blog reports that Rep. Norm Dicks [D-WA], one of EADS Airbus’ most avid foes on Capitol Hill, is likely to succeed Murtha as chair of the subcommittee, and North West Cable News asks the obvious question.

Jan 6/10: At a Pentagon press conference, Press Secretary Geoff Morrell discusses the KC-X v2.0 RFP, among other matters:

“…we are shooting to have the RFP out hopefully by the end of the month, if not early next month. We’re in the process right now of reviewing the comments that were provided… I think we’re still on schedule to get this out in the next few weeks. …no final decisions have been made yet about the RFP, but I think it is safe to say at this point that there will be changes to the draft… We’ve gotten feedback, some of it quite helpful. Some of – some of this we just have realized ourselves. And so I think the team is in the process of correcting mistakes and altering the acquisition strategy a bit, and that will be reflected in the final request for proposal which will likely go out in the – in the next couple or few weeks.

I would add one thing, and that is that whatever changes are being made should not be construed as any attempt to favor anybody. It is — what is being done is we are trying to make the RFP as fair and as transparent as possible, while at the same time providing the taxpayers with the best value for their money and the warfighters the best — the best plane to support their operations… we hope that when this happens that we will have a full and hardy and thorough competition between multiple bidders.”

Jan 4/10: Leeham News offer their 2010 Outlook for Boeing and Airbus, which includes discussion of the KC-X competition:

“We also believe there is a strategic argument, as well as a political one, that supports buying both airplanes because there are simply different mission requirements. But the Pentagon is adamant that it will not split the order… Winning the contract is also critical to the Airbus strategy of establishing a commercial A330-200 production base in the US… Airbus pledged to build the A330-200F [in Mobile, AL] and expectations are that the A330P will follow. But no tanker contract, no US plant. And this is why we believe Boeing and its supporters are fighting so hard to block a tanker award to Northrop. This, we believe, is more important to Boeing than winning the tanker contract, though we also acknowledge Boeing wants the contract on its own merits.

“…The [A330] MRTT is running about 18 months behind schedule for delivery to launch customer Australia. About six months was due to customer change orders, according to the RAAF and EADS. The balance rests with developmental issues.

“…Because of the need for a 787 production Surge Line (see 787 discussion below), the current 767 line will be relocated to the aft part of the bay it now occupies. A Lean production line will be implemented, reducing unit costs by about 20%. Relocation begins this year and will be completed next year… If Northrop stays in, we still think Boeing will submit only a KC-767 proposal… We remain concerned that Boeing has yet to deliver the KC-767 to Italy, now some four years late. We are told problems remain with the centerline hose-and-drogue system… [and] that issues remain with the wing-mounted refueling pods, though Boeing says these have been fixed. Although Boeing intended to deliver the first of four tankers to Italy last year… that this still has not happened indicates all is not well. Since the US tanker is similar to the Italian tanker, we remain skeptical about the program… Boeing is still not forecasting any dates concerning these remaining milestones [for Italy].”

NGC

Dec 1/09: Northrop Grumman’s President and Chief Operating Officer Wes Bush sends a letter to Department of Defense undersecretary for acquisition, technology and logistics Ashton Carter. As written, it says, the terms of the KC-X RFP imposed a structure that, in Northrop Grumman’s opinion, favors smaller planes like Boeing’s, and:

“…places contractual and financial burdens on the company that we simply cannot accept… As a result, I must regrettably inform you that, absent a responsive set of changes in the final RFP, Northrop Grumman has determined that it cannot submit a bid to the department for the KC-X program.”

Pentagon spokesman Bryan Whitman replied that both manufacturers wanted changes that would favor them, and contends that:

“The Department has played this right down the middle… [we] cannot and will not change the warfighting requirements for the tanker to give advantage to either competitor… The department wants competition but cannot compel the two airplane makers to compete.”

Alabama’s Republican governor Bill Riley has a different take:

“The Obama administration has corrupted the tanker selection process with a blatantly unfair competition… The question is why is this RFP so radically different than the one Northrop Grumman won last year?”

A final RFP is expected in January 2010, but each program has hundreds of suppliers across the USA. Refusal to submit would trigger a very large political battle in Congress, one focused on the acquisition process itself. It remains to be seen whether it is possible for a single-winner tanker process to successfully obtain American Congressional approval and funding for its choice, in the face of a transatlantic competitor whose American partners saw billions of dollars in concrete business snatched away, and a domestic heavyweight with its own deep supplier and congressional networks. Northrop Grumman’s Letter [PDF] | Agence France Presse | Bloomberg | NY Times | Politico | Reuters | Wall Street Journal | Aviation Week | Defense News.

Nov 25/09: Flight International reports that one of Australia’s KC-30Bs refueled a pair of Spanish EF-18A Hornet fighters at the same time, using its hose-and-drogue refueling system.

Nov 10/09: Aviation Week headline: “Boeing, Northrop Sour On KC-X Draft RFP.”

Nov 10/09: One of Australia’s KC-30B/ A330 MRTTs performs the 1st fuel transfers with its all-digital 905E hose and drogue system, using its left and right under-wing pods to transfer more than 9,200 lbs of fuel to a “NATO” (likely Spanish) F/A-18 fighter. The first of Australia’s 5 KC-30Bs will be delivered to Australia in mid-2010. EADS release.

Nov 2/09: The Lexington Institute’s Loren Thompson writes that the EADS/Northrop Grumman bid has become a question, rather than a certainty:

“Last week, one of the two teams competing to provide the Air Force’s future aerial-refueling tanker launched an unusual campaign to overturn the service’s strategy for buying the plane. Northrop Grumman and its European partner Airbus signaled that they don’t believe they have a plausible chance of winning under the proposed terms, and began building the foundation for a formal protest. What’s unusual about the move is that competitor Boeing hasn’t been all that happy with the revised tanker solicitation either, but Northrop has elected to pursue an aggressive strategy that is sure to anger its Air Force customer. Here’s why Northrop is willing to take that risk…”

Oct 29/09: Sen. John McCain [R-AZ] sends a letter to Defense Secretary Robert Gates, Pentagon acquisition czar Ashton Carter, and USAF Secretary Michael Donley, asking questions about the KC-X v2.0 source selection process. He asks about the use of fuel usage rates and construction needs, but not full probable lifecycle cost, in the cost calculations, asks if any of the requirements considered mandatory in Round 1 were discarded RFP v2.0, wonders if the pricing requirements in the draft RFP would “…not favor mostly smaller airframes, and asks how the proposed pass/fail rating can “provide for an assessment of relative developmental and integration risk among the offerings.”

The final v2.0 RFP was supposed to be released around the end of November 2009, but delays out to January 2010 are reportedly a possibility. Aviation Week.

Oct 21/09: Team EADS. An A330 MRTT equipped with the ARBS in-flight refueling boom passes fuel to an in-flight aircraft for the first time. A Royal Australian Air Force KC-30B flew a 4:30 test flight, with more than 3,300 pounds of fuel transferred to 2 Portuguese Air Force F-16s during 13 contacts. Other systems tested included the boom’s fly-by-wire stability and 3-D vision system. EADS | Australian Defence Magazine.

Oct 2/09: Sen. Jeff Sessions [R-AL] says he will introduce an amendment to the FY 2010 Senate defense spending bill (amendment 2610 to S. 1390, currently before the Senate Armed Services Committee). When introduced, it would block the use of funds for the U.S. Air Force’s KC-X competition, unless the service agrees to disclose pricing data about Boeing’s proposal in 2008 to rival Northrop Grumman, just as Northrop Grumman’s data was disclosed to Boeing after Boeing’ asked for an explanation of its loss. Sen. Sessions release | Aviation Week | See also Sept 29/09 entry.

Oct 1/09: KC-10. In a stunning upset, Northrop Grumman beats Boeing for a 10-year, $3.8 billion contract to service the global KC-10/KDC-10 tanker fleet. Boeing subsidiary McDonnell Douglas built the planes, modified them, and had serviced them since their induction in the 1980s. By all accounts and metrics, service quality was high – which is why some analysts see the loss as symptomatic of deeper problems in Boeing’s relationship with the USAF.

FY 2009

Draft RFP 2.0.

Boeing: early KC-46A concept

KC-46A & B-1B
(click to view full)

Sept 29/09: Major procurement error. As legislators connected with Boeing push the USAF regarding the recent WTO ruling, Northrop Grumman puts out a statement of its own, citing issues with the process:

“Northrop Grumman continues to be greatly concerned that its pricing information from the previous tanker competition was provided by the Government to its competitor, Boeing. Access to comparable pricing information from Boeing has thus far been denied by the Pentagon. With predominant emphasis placed on price in this tanker re-competition and Northrop Grumman again proposing its KC-45 refueling tanker, such competitive pricing information takes on even greater importance. It is fundamentally unfair, and distorts any new competition, to provide such critical information to only one of the bidders. The company will continue to work with its customer to fully resolve this issue.”

The USAF had provided this data to Boeing after Boeing had lost, as part of the USAF’s requested debriefing. The Pentagon has dismissed Northrop Grumman’s claim on the basis that the disclosure to Boeing was in accordance with regulations, and that “the data in question are inaccurate, outdated and not germane” to the new bid, which is a different competition. Clearly, Northrop Grumman continues to disagree; if the impasse continues, the question may become whether the GAO disagrees during a future appeal. Northrop Grumman | Aviation Week | recent Seattle Post-Intelligencer.

Protoccol breach

Sept 29/09: Alabama’s Press-Register puts out an editorial supporting a split-buy and speeded-up production, which legislators like House Appropriations Committee Chair John Murtha [D-PA] continue to support:

“With a defense contract potentially worth $40 billion at stake, expect both sides to fight over every clause and nuance they think might favor their opponent. Right now, Boeing and Northrop have 60 days to comment on the draft guidelines; this is only the first stage of the contest… By the time the lawyering and politicking are over, at least a few years will have elapsed. So here’s one more plea for a split contract.”

Sept 25/09: The USAF releases the KC-X v2.0 draft RFP, re-starting the competition. The KC-X Round 2 RFP remains structured as a “winner take all” competition, and retains its target number of 179 aircraft, will full-rate production of 15 per year beginning by the 3rd year (Lot 3 of up to 13). Each contender will provide a fixed-price proposal to develop and deliver 4 Engineering & Manufacturing Development (EMD) planes, followed by the first 64 aircraft and necessary spares. It will also submit an upper limit on the price of the remaining 111 tankers, and 5 years of initial support.

Assuming that legal and political delays don’t get in the way, first production delivery is now planned for 2015, with Initial Operational Capability in 2017. More information on the RFP’s evaluation structure can be found in the section “KC-X RFP v2.0: The New Structure.”

Next comes the 60-day comment period, after which the formal RFP can be expected. The bidders will then have 60 days after that final RFP release to submit their bids, and the government will have 120 days to evaluate them. A decision is currently expected in mid-2010. FedBizOpps RFP #FA8625-10-R-6600 | USAF RFP release presentation | DoD briefing re: competition, incl. Slides [PDF] and Q&A session | USAF | Boeing statement | Northrop Grumman statement | Agence France Presse | Aviation Week and AVWeek Ares re: selection process | Aviation Week re: people involved | Business Week | CBS WKRG in Pensacola, FL | Government Executive | The Hill | Leeham News & Comment aviation analysts | Military.com | Nextgov | Seattle Post-Intelligencer analysis | WSJ: Boeing brings flight simulator to Capitol Hill.

Draft RFP to restart KC-X

Sept 25/09: The USAF’s last serving KC-135E aerial tanker touches down at Davis-Monthan AFB near tucson, AZ, after its final flight. All remaining KC-135s are now KC-135Rs. USAF release.

KC-135E retires

Sept 16/09: US Secretary of Defense Gates says that he is giving the new leaders he’d installed at the Air Force the final say in the $40 billion tanker deal. This is a reversal from the Round 1 arrangements after the GAO ruled that the USAF had not followed its own criteria, and the US Department of Defense took over direct management of the program. On the other hand, it does put the USAF on the firing line instead of the DoD, in order to absorb any initial hits in what’s sure to be an intense political fight.

Other reports add that the revised KC-X proposal is due “in a few weeks.” USAF | Boeing statement | Defense News | Government Executive magazine | Inside Defense | Agence France Presse | Business Week | NY Times | Reuters | Seattle P.I. offers analyst’s view.

Sept 15/09: Aviation Week reports that keeping the existing KC-135 fleet in the air will become increasingly expensive:

“…at AMC, planners are wrangling with how to keep the KC-135s flying until as late as 2043… outgoing AMC chief [Arthur] Lichte points out that maintenance crews sometimes work 7 hr. for every hour of KC-135 flight. “Every year we don’t get tankers, it is costing us $55 million right off the top,” Lichte says. “When you get out to about 2018 and 2020, what started out as about $2 billion a year to maintain the KC-135 fleet goes all the way up to $6 billion… we continue to do everything we can to make sure don’t have an Aloha Airlines where the skin peels back or a TWA 800 [type incident] where frayed wires cause an explosion in the fuel tank… In total, aging-related costs are expected to add at least $17.8 billion to the price of maintaining the KC-135 for 40 years.”

The increase in projected maintenance costs is attributable mostly to fuselage skin and wiring checks, and corrosion issues which are already a significant contributor (30%-50%, by some reports) to depot maintenance costs. Meanwhile, access to KC-10 replacement parts is a worry, and the KC-10 boom control unit is becoming unreliable and should be replaced.

KC-135 costs rising

Sept 15/09: Flight International reports that KC-X Round 2 may see a supplier shakeup on the Boeing side:

“Boeing officials are determined to set “aggressive price targets” for selecting suppliers and even manufacturing locations… Boeing’s quest for cost-savings has also reopened the 777’s engine supplier to competition… all three certified engines – the GE90, Pratt & Whitney PW4000 and Rolls-Royce Trent 800 – will be considered if Boeing decides to offer the KC-777. However, engines that have not been certified on the 777, such as the GEnx family, have been ruled out. “We don’t think there’s enough time for a certification programme,” Lemaster says… If Boeing decides to propose the KC-767 in the next round, the structures and control systems will come from the same aircraft type, Lemaster says.”

Sept 14/09: US Ar Force Secretary Michael Donley says the WTO’s ruling will have no effect on the USAF’s process, as Airbus’ counterclaim is still pending, and so is the EU’s expected appeal.

A day later, 47 American politicians send a letter to President Obama that says: “Buying Airbus tankers would reward European governments with Department of Defense dollars at the same time that the U.S. Trade Representative is trying to punish European governments for flouting international laws.” Mobile Press-Register | Seattle Post-Intelligencer | Reuters via Forbes | Business Week | Seattle P.I. re: letter | Seattle P.I. offers contrasting views re: finer points of WTO trade dispute.

Boeing KC-X stats

KC-X past & candidates:
Boeing Slide
(click to view full)

Sept 14/09: In a briefing at the Air Force Association’s 2009 Air & Space Conference and Technology Exposition, Boeing officially acknowledges that the Boeing 767 and 777 are both potential KC-X candidates. They also launch their own web site, UnitedStatesTanker.com, to promote their “KC-7A7” tanker bid. Boeing release | Boeing briefing [PDF]

Sept 8/09: EADS chief executive Louis Gallois tells the French newspaper La Tribune that: “Our objective is to be in the [KC-X] competition. We are totally determined to be in the running, unless it appears that the request for proposal is biased.” Source.

Sept 4/09: The World Trade Organization issues an interim ruling that the $4 billion in aid Airbus received from European governments to develop the A380 super-jumbo passenger jet constituted illegal subsidies.

Technically, the WTO ruling could empower the U.S. to levy tariffs either against Airbus or other European imports, equal to the amount of the improper subsidies. Legally, the EU is expected to appeal the ruling, Airbus has complaints of its own on tap, and any firm action remains years away. Business Week | bnet.

July 9/09: Stephen Trimble of Flight International highlights a recent podcast interview with Boeing tanker spokesman Bill Barksdale, which seems to show a lot of enthusiasm and prep work at Boeing around the KC-777. Excerpt:

“BARKSDALE: The 777 as a tanker is just so much more capable than anything it’s got as a peer. And I know that sounds like a bit of bravado, but… I’ll give you a couple of examples. If you compare them, the 777 would provide – deliver – however you want to say it – 23% more fuel than the KC-30. It could carry 44% more payload – more cargo – in the back. And it also would carry about 42% more passengers in the back as well. So those are very generic, very general kinds of numbers… If the air force really wants to go in that direction, the Boeing company has spent a lot of time in the last year preparing for that, knowing that we have a real, true, large tanker that, like I said, is comparable in size to the KC-30. And, yet, you get so much more for your money.”

June 16/09: Northrop Grumman CEO Ronald D. Sugar, and EADS CEO Louis Gallois, issue a joint statement re-affirming their joint commitment to the KC-45 Tanker team.

June 15/09: Bloomberg reports that Boeing is preparing to submit a KC-777 for KC-X v2.0, but a DoD Buzz story clarifies. It turns out that Boeing is preparing to offer a KC-777 option if the revised requirements put a premium on cargo capability or fuel offload amounts, but the firm hasn’t made a decision and won’t until the RFP comes out. The firm had considered a KC-777 before the initial KC-X RFP as well, but the RFP’s lack of extra points for exceeding USAF specifications led Boeing to go with its smaller, cheaper, and more fully developed KC-767 instead. DoD Buzz adds:

“Still, a Boeing 777 bid raises all sorts of questions. Given the problems Boeing has had reducing the vibrations afflicting its refueling pods on the 767, and the enormous technical and engineering challenges of refitting the 777, can the company get a plane in shape in time to fill the Air Force’s first tranche of 179 planes?… But it may be that Boeing is largely conceding the first tranche of planes to Northrop and aiming for the larger follow-on buy.”

The DoD Buzz report adds rumors that Northrop Grumman may walk if the revised RFP is seen as weighted in Boeing’s favor – again, a parallel with the firm’s rumblings before the initial KC-X RFP was issued:

“…there are rumors that Northrop is weighing its commitment to the tanker program, which has cost the company financially and politically. Two sources have told me that Ron Sugar, the company’s CEO, will walk away from the competition should the new RFP appear weighted too heavily in Boeing’s favor. This could, of course, be part of the company’s gaming efforts to ensure that the Air Force does include analysis such as best value as it makes its choice. Meyers made clear, as does his colleague Janis Pamiljans in the video below, that the Air Force must include “best value” as a key component of the service’s tanker analysis.”

June 9/09: The USAF’s role in KC-X v2.0 is still up for debate. Military.com’s DoD Buzz reports that Defense Secretary Robert Gates is still deciding whether the Air Force would lead the renewed competition, or whether it would remain with the Office of Secretary of Defense. Either way, however, Gates said that former Raytheon lobbyist and current Deputy Defense Secretary Bill Lynn would take a “very close interest” in the program.

May 27/09: The Project on Government Oversight NGO explains some of the hidden variables behind decisions about who should run the program:

“…this isn’t only a debate over who will be ultimately responsible for the program, but that it will also determine how much this program will be impacted by the new Weapons Acquisition Reform Act of 2009. One of the major revisions to the Senate’s initial version of the bill in the Senate Armed Service committee’s mark-up was changing language that would require the newly established Director of Independent Cost Assessment to conduct independent cost assessments for all major defense acquisition programs (MDAPs) to only those programs where the Under Secretary for Acquisition, Technology and Logistics (AT &L) is the Milestone Decision Authority (MDA)… But as a result of this change in mark up, if DoD chooses to give the Air Force management of the tanker program, there will be no mandatory role for the new Director of Independent Cost Assessment to provide oversight and implement policies and procedures to make sure that the cost estimation process is reliable and objective. One can’t help but wonder how much DoD had the tanker program in mind when requesting this change to the legislation.”

April 6/09: US Defense Secretary Gates announces his FY 2010 budget recommendations, which will include a KC-X RFP in summer 2009.

April 6/09: The Lexington Institute raises warning flags about the new acquisition process:

“Despite Obama Administration rhetoric about openness in federal contracting, the new and improved tanker selection process has all the transparency of the FBI’s witness protection program. The performance requirements for the future tankers were blessed by the Pentagon’s Joint Requirements Oversight Council with almost no input from industry, and now the acquisition strategy is being crafted in much the same way. If you were planning to spend $100 billion over the next 30 years on a new aircraft fleet, wouldn’t you want to check with the only two qualified suppliers to determine whether your terms and specifications were reasonable? We have been here before… Many of those problems could have been avoided if the industry teams had been kept informed on how the selection process was unfolding… The current buildup to a re-competition is being carried out with even greater secrecy.”

At this point, with Northrop Grumman and its suppliers believing that a huge contract was taken away from them, and Boeing treating the lobbying as a life-or-death issue, the impact may be tangential. The political reality is that lack of transparency can make the process worse, but even perfect transparency won’t remove the fundamental political bottleneck.

March 17/09: NGC endorses split-buy. A Northrop Grumman release offers figures from a KC-135 Economic Service Life Study, and claims that for each KC-45 that enters service, USAF operating costs would drop by $7 million per year, assuming replacement of 2 KC-135s with each A330 MRTT inducted. It adds:

“Congressmen John Murtha (D-PA) and Neil Abercrombie (D-HI) commented recently the only way to get badly needed tankers to our warfighters quickly is through a dual procurement acquisition process… According to Northrop Grumman analysis, a dual procurement scenario could replace the capability of the entire Air Force KC-135 fleet by the year 2022 – seven years sooner than best case single procurement strategy. Dual procurement eliminates the need to re-skin the KC-135 aircraft.

By procuring 24 aircraft per year from two contractors rather than 15 per year from a single source, as is the current Air Force budget plan, the service could save $7.2 billion in tanker Operating and Support (O&S) costs between 2012 and 2022 compared to the O&S costs associated with a single procurement strategy. Through dual procurement, the Air Force saves $10.2 billion in tanker O&S between 2012 and 2029, compared to the O&S costs associated with a single procurement strategy. [Our product is better, but]… if Congressmen Murtha and Abercrombie are correct the only way to get tankers to the warfighter quickly is through a dual procurement strategy, Northrop Grumman will support the effort.”

The crunch, of course, is that 9 more aircraft per year, at about $200 million each, adds $1.8 billion per year to actual spending. That’s another $19.8 billion from 2012-2022, or $30.6 billion from 2012-2029. The difference between those figures, and projected savings over the same time period, must come from somewhere. That means either expansion of the overall military budget, or dollars taken from other military programs. Both options are unlikely, and difficult.

March 13/09: An Inside the Air Force article entitled “Report: KC-135 Maintenance Could Reach $3 Billion Per Year by 2040” says that KC-135 maintenance costs will escalate by almost 50% over the next 30 years, and cost twice as much as new tankers. The KC-135 Economic Service Life Study claims that it will end up costing the Air Force more than FY2000$ 103 billion to operate and maintain the KC-135s between 2001-2040. Source.

March 11/09: Reports surface that the Obama administration will propose a 5-year delay to the USAF’s aerial tanker program, as US OMB recommendations leak to the general press. The Pentagon is not bound by those recommendations, and US Secretary of Defense Gates is quoted as saying that:

“In the days to come, any information you may receive about budget or program decisions will undoubtedly be wrong because I intend to wait until the end of our review process before making any decisions.”

Assuming that the documents really do propose a 5-year delay to the KC-X program, it is not clear whether this is a classic “Washington Monument” move, proposing a cut that the weight of Congress interests are almost certain to reverse, or a genuine decision within a zero-sum set of budget decisions. In Washington, of course, it could even be both. Washington Post | Seattle Post-Intelligencer | Seattle Times | Grand Forks Herald | Bloomberg News | MSNBC | Agence France Presse.

March 11/09: Democratic Party congressmen John Murtha [D-PA] and Neil Abercrombie [D-HI] begin publicly proposing the split-buy idea that has been floated quietly in the background for several months now. Reuters | Reuters Update.

Feb 26/09: Military.com’s DoD Buzz reports that a Pentagon Joint Requirement Oversight Council met today to consider the new KC-X requirements:

“From what little I have heard about the requirements, it seems pretty clear that the Air Force has compressed and simplified the requirements to avoid the likelihood of another award protest but has not changed its mind about what capabilities are needed… But Rep. Jack Murtha’s plan to split the buy – and avoid what would seem to be an otherwise unavoidable second protest – would seem to allow both companies some breathing room… the Air Force’s opposition may be at an end – at least for the initial purchase.”

Murtha [D-PA] has been at the center of ethical investigations over his career, but he remains a powerful member of the Democratic Party. He chairs the House Appropriations Committee’s Defense Subcommittee.

Feb 25/09: USAF Transportation Command leader Gen. Duncan McNabb testifies to a joint hearing of the House Armed Services Committee’s Seapower and Air and land forces subcommittees. He reiterates KC-X as the USAF’s top priority, and says that further delays in replacing the KC-135 fleet would add significant risk to the U.S. military’s ability to quickly move troops and firepower rapidly to the globe’s combat zones. Reuters, via Forbes.

Jan 29/09: The US government’s Office of Management and Budget submits a list of potential defense program cuts in its guidance to the US Defense Department. One of the suggestions is reportedly a 5-year delay of the KC-X program. The Pentagon is not bound by these suggestions, but the recommendations will become news in March 2009, igniting controversy and lobbying. Source.

FY 2008

Boeing protest; cancellation.

Capitol Building

Sept 22/08: Sen. Richard Shelby [R-AL] fires a broadside in a Washington Times op-ed:

“Two months from Election Day, politics seem to be everywhere we turn. However, one place we should not see politics is in our Department of Defense (DoD) acquisition process. The process to select the new Air Force tanker fleet has become so politicized that DoD allowed parochial and business interests to keep the Air Force’s top acquisition priority from the pilots who need it. The long fight over the tanker contract proves that the acquisition process is fundamentally and significantly flawed… Politics just cancelled a competitively awarded contract, solely because Boeing was not the winner. Defense acquisition policy has been stated: If it is not a Boeing plane, DoD is not going to buy it.”

Sept 18/08: A Washington Post story reports that:

“John Young, the undersecretary for acquisition, technology and logistics, said in an interview at the Pentagon yesterday that under the tanker proposal from Northrop Grumman and its partner European Aeronautic Defence & Space, developing the first 68 aircraft would have cost $12.5 billion, compared with $15.4 billion under Boeing’s plan.”

Sept 10/08: The Pentagon announces that Defense Secretary Robert M. Gates has canceled the competition for the $35 billion Air Force tanker contract:

“It has now become clear that the solicitation and award process cannot be accomplished by January. Thus, I believe that rather than hand the next administration an incomplete and possibly contested process, we should cleanly defer this procurement to the next team… It is my judgment that in the time remaining to us, we cannot complete a competition that will be viewed as fair and competitive in this highly-charged environment… I believe the resulting cooling-off period will allow the next administration to view objectively the military requirements and craft a new acquisition strategy for the KC-X as it sees fit.”

Cancellation

Sept 3/08: Gen. Lichte of USAF Air Mobility Command says that he expects a protest after the final round 2 RFP is released. He hopes it doesn’t happen. But:

“I mean this is a lot of money, I understand the business nature of this. But I don’t understand how at some point you stop and say, this company wins, and this company loses, or this company is successful and this company is not. I don’t know how we get through something like that. With the poisonous nature of all the comments that are out there right now, I don’t know how we make peace with everybody to say, okay let’s go forward.”

He also said that he does not want a split buy…

“However, if you were to tell me that was the only way to get out of [the current situation] then I’d take it… We need a new tanker now. I don’t care which one it is. And we need to get on with this quickly.”

Military.com | Agence France Presse | AP | CBS | Reuters.

Aug 14/08: Jerry Cox is a former procurement policy counsel in the U.S. Senate, and now holds the title of managing director of The Forerunner Foundation. At, least according to the article byline in the Seattle Post-Intelligencer for “Tanker choice in mathematical terms“. The core claim of the article is as follows:

“The Air Force knows a tanker accomplishes nothing by flying from Point A to Point B, so what really matters is the ratio of delivery. How many gallons will the plane deliver for every gallon it burns? That’s a tougher problem, but it’s hardly trigonometry. Northrop showed the Air Force it can deliver almost two pounds for every pound it burns, while Boeing delivers only 1.6 pounds. That’s a 22 percent edge for Northrop, and the numbers hold up, regardless of the trip length.”

What the newspaper did not mention is that Cox also heads up a lobbying firm called Potomac Strategy Associates. DID spoke to Jerry Cox, however, and he told us that his PSA has not been employed by any firm in conjunction with the aerial tanker competition.

Aug 11/08: Aviation week reports that Boeing is strongly considering a refusal to bid as its response to the revised KC-X RFP.

That response would leave the field open to EADS/Northrop Grumman in a formal sense, but the political weight of that kind of protest move would force the Pentagon to think long and hard before signing a contract under those circumstances. Until Boeing makes a firm decision, of course, its bid team must continue working full speed ahead.

Aug 6/08: New draft RFP. The USAF has issued a new draft of its RFP, and appears to be adopting an approach of minimum required compliance. On the surface, there are 2 major changes. Fuel costs over a plane’s 40-year lifetime will be considered, and full credit will now be given for exceeding the stated requirements in key areas like cargo capacity, fuel offload, et. al. Neither was true under the old RFP. The catch is that different levels of importance are being assigned to various types of costs, with development and production cost estimates weighted more heavily than long-term projections for maintenance and fuel costs. The second major change around exceeding performance limits simply makes the USAF’s original evaluation approach the competition’s officially announced approach, instead of a violation of the competition’s terms.

Under those terms, Boeing is likely to lose again – which may trigger a follow-on protest upon the release of the revised RFP. The planned time line for moving forward is as follows:

* Aug 6-13: DoD officials will take a week to discuss elements of the draft with Northrop-Grumman and Boeing. Expect a lot of back and forth over the terms of the RFP, including efforts by members of the (currently recessed) Congress.

* Mid-August: DoD plans to issue the final RFP amendment, with just 45 days for renewed submissions. Note that this time frame would make an airframe switch very difficult, due to the hundreds of pages of documentation, cost information, and design work required.

* Early October 2008: Renewed submissions due.

* October to late November: Discussions with the companies about their proposals.

* Early December: Final proposal revisions for “best, final” offer.

* Early January 2009: Decision made and announced. If Boeing wins, the existing contract is canceled and a new one is signed. If Airbus/NGC win again, the current stop-work order is lifted.

It’s important to note that the US DoD’s desired schedule, and what politics, appeals, et. al. actually end up dictating, may end up being 2 different things. On a political level, however, introducing the revised RFP when Congress is in recess, and not issuing a decision until after the elections, will help to lower elected representatives’ political leverage. What it will not do is provide full insulation, since the decision is certain to be an important election issue in some states. The first days in a new Congress’ term also tend to provide some political insulation for issues of this type, since members are busy with other things. Nevertheless, it can also be a double-edged sword. Exceptions do occur if the issue in question is a big enough priority for enough elected representatives. In that case, the first days of a term can also be the stage for dramatic political actions whose fallout would be considered much more carefully later in their term.

See also: KC-X RFP, revised draft | US Armed Forces Press Service | Boeing statement et. al., via CNBC | NGC statement via MarketWatch | CQ Politics | Politico re: guerilla marketing | Leeham Companies LLC | Defense News | Aviation Week | Bloomberg | Business Week | Christian Science Monitor | Agence France Presse | Money Times of India | Seattle Post-Intelligencer | Seattle Times | Mobile Press Register | Birmingham News | Pensacola News Journal.

July 9/08: Let Round 2 begin. American Secretary of Defense Robert Gates announces that the KC-X competition will be re-opened, with at least one important difference: the Air Force won’t be running it. Meanwhile, Northrop-Grumman has been ordered to stop work on its contract.

Undersecretary of defense for acquisition, technology and logistics John J. Young Jr. will be in charge of the acquisition, and will appoint an advisory committee to oversee the selection process. , and a modified request for proposal could be issued before the end of July 2008, with a decision expected by year’s end.

Boeing’s statement welcomes the news, and claims that life-cycle costs including fuel will now be considered in the competition:

“However, we remain concerned that a renewed Request for Proposals (RFP) may include changes that significantly alter the selection criteria as set forth in the original solicitation. As the Government Accountability Office reported in upholding our protest, we submitted the only proposal that fully met the mandatory criteria of the original RFP… we will also take time to understand the updated solicitation to determine the right path forward for the company. It’s encouraging that the Defense Department intends to take steps …that, among other things, fully accounts for life-cycle costs, such as fuel…”

The new competition will be challenging for all concerned, especially since it adds an element missing from the last round: European expectations, raised by the initial win, could create larger trade and defense industry ramifications if the new competition is perceived to be biased against Airbus’ offering. Meanwhile, political involvement and pressure within the USA is guaranteed to be intense, and every item from the selection criteria onward can expect contestation. US DoD | Boeing release | Northrop Grumman release | Alabama Press-Register | Montgomery Advertiser | Seattle Times | WIRED Danger Room | CNBC | Hartford Courant | AP | Aviation Week: L